Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Construction $ 1,668.858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO 9/14/98 $ 102,705.00
Amount approved by CO 9/21/98 $ 28,442.00
Amount approved by CO on 10/22/98 $ 26,483.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/1/98 $ 125,453.00
Amount approved by this CO 27.821.00
Total construction cost approved $13,343,094.00
Less Landlord contribution $ 1.668.858.00
Amount chargeable to_the City $11,674,236.00
Balance remaining in Budget $ 384,892.00
If you have any questions, please call Glenn Pymento at 212-669-8094. Thank you for your cooperation.
Sincerely,
/Richard T Ramos
Executive Director of Space Design/DRES
c:
G, Pymento, DRESe^;^
V. Castagnola, DRES
J. Domingvez, DRES
M. Mathew, DRES
J. Menasce, DRES
W. Weems, Silverstein Properties, Inc.
c:Giliberti5/mm/kc
NYC-WTC_000171886
OCR can misread numbers and units. Confirm readings against the page image before using them.