The following is a breakdo wn of the project’s budget:
Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $117,684.00
Amount approved by CO on 8/11/98 $7,000.00
Amount approved by CO on 9/14/98 $102,705.00
Amount approved by CO on 9/21/98 $28,442.00
Amount approved by CO on 10/22/98 $26,483.00
Amount approved by CO on 10/30/98 $42,887.00
Amount approved by CO on 12/1/98 $125,453.00
Amount approved by CO on 12/29/98 $27,821.00
Amount approved by CO on 1/4/99 $3,941.00
Amount approved by CO on 1/25/99 $78,288.00
Amount approved by this CO $22,721.00
Total construction cost approved $13,448,044.00
Less Landlord contribution $1,668,858.00
Amount chargeable to the City $ 11,779,186.00
Balance remaining in Budget $279,942.00
If you have any questions, please call Glenn Pymento at (212) 669-8094. Thank you for your
cooperation.
Sincerely.
Qchard J. Ramos
Executive Director of Space Design/DRES
cc: G. Pymento, DRES M. Mathew,
V. Castagnola, DRES J. Menasce, DRES
J. Domingvez, DRIiS W. Weems, Silverstein Properties, Inc.
c:\nini\silverstein prop giliberti3.doc/bw