ROBERT B. SAMUELS INC.
June 23. 1998
Ambassador Construction
317 Madison Avenue
New York, NY 10017
Attn: Mr. Jack Klein
Re: Mayor’s office of Emergency Management
7 World Trade center
1st, 7th & 23rd Floor
New York, NY
Project 96-346
Gentlemen:
Please refer to the letter from The city of New York dated June
18, 1998. Our reply is as follows:
1. (a) Substitute Cabling from EMT to BX
credit:; $ 30,000.00
(b) Delete Tel and Data Cabling per Section l_670Q
Credit: $ 198,962.60
(C) Eliminate aZv Equipment as Indicated in Exhibit. A
No credit - not included in our proposal. Please refer
to our qualifications Note #22.
(d) Breakdown
General Foreman for 1040 Hrs @ 106.62
per hour - $ 110,883.00
Assistant Foreman for 805 Hrs ® 91.57 $ 73,717.00
Engineer for 260 Hours a 125.00 • $ 32,500-00
Draftsman for 260 hours ©78.08 - $ 20.300.00
Tools and tool rental • $ 30,000.00
Job expenses $1000/per month, i.e. phone.
drafting, material, blue prints * 6,000.00
Total: $ 273,400.00
continued...