Electrical service proposal, 7 World Trade Center, May 1998

Machine-extracted title · confidence 95%

Contractor proposal for electrical panels, risers, generators, fire alarm, wiring, and lighting work at 7 World Trade Center totaling approximately $3.76 million.

NYC-WTC_000172671–000172674

Folder label: “OEM ®7 World Trade Center®Est. No. 98 - 341KJ/SS

Page image
Scanned page image, NYC-WTC_000172671
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

MAY 19 1998 10:58 FR R.B.SAMUELS 212 213 4089 TO AMBASSADOR P.02/05

ROBERT B. SAMUELS INC.

May 19, 1998 Ambassador Construction 317 Madison Avenue New York, NY 10017 Attn: Mr. Martin Sclineider Re: OEM 7 World Trade Center ESt. NO. 98-341KJ/SS Gentlemen: We are pleased to confirm our proposal as per plans and qualifications listed below: SERVICE, panels, RISERS, GENERATORS CONNECTIONS, TRANSFER SWITCHES AND PARALLELING SWITCHGEAR....$ 1,674,000.00 FIRE ALARM...................... 112,000.00^ POWER WIRING ON 23RD FLOOR...... 361,000.00 MOTOR WIRING.................... 97,000.00 LOW VOLTAGE WIRING INCLUDING RISERS 771,000.00 LIGHTING........................ 498,000.00 MISCELLANEOUS WORK............... __ 55,110-0^X1^ TEL/DATA CABLE.................. C^ZZSjlQOO^. > itt*- BASE BID: THREE MILLION SEVEN HUNDRED FIFTY NINE THOUSAND AND 00/100 DOLLARS. OUR BID IS BASED ON; 0^ 1. Architect; Swanke Hayden Connell Ltd. OyOC'OyO 2. Engineer; Coaentini Associates - Drawings T-1, A-EG-23, A-1-1, A-7-1. 23’1 to 6, 98-1, DO to 12 - dated 4/6/98, M-01, 07, 03, 01 dated 4/6/98. E-OOl, 1.01, 1.07, 1.23, 2.23, 1.48, 3.01, 4.01 to 4.03, E6.01 & 2 dated 4/6/98. Pl.01, 1.07, 3.23, 4.23, 5.23 dated 4/6/98. FPl.Ol, 2.07, 3.23, 4.23, 5.23, 6.23 dated 4/6/98. S-1 to S-5 dated 4/6/98. AV-1 to 4, AV-EO to 15-5, AV-Sl to S8 dated 4/6/98. TC-lOO, 101, 103, 103A, 103B dated 4/6/98. 0382001 to 5 dated 3. A tax exempt fob. '

1

aco OA'Dt' ATf'C'lvmB' Cr»TmJ /MT75Ar VrADt' mnirt / eoc cnn , T?* V. NYC-WTC_000172671

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000172671Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Construction cost estimate, 7 WTC OEM, Feb 1998 · Box 7DCAS

NYC-WTC_000170825

Ambassador Construction submits a $10.8 million cost estimate for demolition and fit-out work at the Mayor's Office of Emergency Management.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.938

machine-extracted · confidence unavailable · Check page ↗
Fax transmission log for 7 WTC project, Jan 1995 · Box 7DCAS

NYC-WTC_000173652

Log of incoming and outgoing faxes between Ambassador Construction and the Office of Emergency Management regarding project communications.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.933

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →