08/31/98.- MON .15:34 FAI 2126458^ - ■, i ,'KABACK AMBASSADOR I21002
2. This time includes refabricating and installing new duct as
required due to this change on Page #2:
a. 1 eketcher, 1 hour at $98.00/hr. / $ 98.00
b. 1 shop fabricator, 6 hours at
$98.00/hr. 588.00
c. 2 field men. 5 hours at $98.00/hr. 2 980.00
d. Material 120.00
SUBTOTAL $1,786.00
10% Overhead 178.60
10% Profit 196.46
$2,161.06
X 15 Locations
TOTAL $32,415.00
3. New due: per Page #3:
a. 1 Bcetcher, 1/2 hours at $98.00/hr. $ 49.00
b. 1 s lop fabricator, 4 1/2 hoUrs at -
$98.00/hr. 441.00 ‘ I ?
C. 2 field men, 3 1/2 hours each at
98.)0/hr. 686.00
d. Mat jrial 95.00 ^'
SUBTOTAL $ 1,271.00 '
10% Overhead 127.10
10% Profit : 139.80
$ 1,537.90
X 5 Locations
TOTAL $ 7,689.50
4. D-uctwori: per Page #4 :
a. 1 sketcher, i/4 hour at $98.!oo/hr. $ 24.50
b. 1 sliop fabricator, 2 1/2 hours at
$98 00/hr. , 245.00
c. 2 f;.eld men, 2 hours at $98.i00/hr. 392.00
d. Material 55.00
SUBTOTAL $ 716.50
10% Ove rhe aid 71.65
10% Profit : 78.81
$ 866.96
X 32 Locations
TOTAL $27,742.72