55 Removal & reinstallation of electrical work
due to routing of fuel oil pipe line. $ 34,954.00 $ 29,000.00
57 Additional equipment & labor for
security work as per SHCA memo
dated 12/17/98. $ 68,613.00 $ 63,000.00
58 Labor for moving computer equipments. $ 5,506.00 $ 5,506.00
59 1 duplex outlet on V floor with wiring
in existing 4 conduit. $ 10,948.00 $ 10,948.00
60 Close gap at steel in hurricane wall
with 16 gauge steel plate as per FSK-54. $ 8,114.00 $ 8,114.00
61 Mag lock override button for doors at toilet
rooms, water storage room, bunker rooms
and door leading to bunker room area. $ 2,785.00 $ 2,400.00
62 Roof repair as per details at new curb
from Kemper systems. $ 9,679.00 $ 9,679,00
63 Additional electrical work as per RB
Samuel’s work orders. $ 1,912.00 $ 1,912.00
64 Additional electrical work as per
RB Samuel’s work orders. $ 7,114.00 $ 6,500.00
66 Press room floor and podium work. $ 15,460.00 $ 14,800.00
67 ’Various electrical changes per as
RB Samuel’s work orders. $ 2,894.00 $ 2,894.00
69 F & I closer, roof chain & provide
additional keys. $ 780.00 $ 672.00
70 Three 28 dia and two 21 dia cast
magnum plaques. $ 6,114.00 $ 6,114.00
71 Two 3 phase 30 amp wiring for
circulating pump. $ 4,579.00 $ 4,579.00
TOTAL $236,583.00 $220,262.00
In view of the above, an amount of $220,262.00 in hereby approved, subject to audit, for the above change
orders.
The following is a breakdown of the project’s budget:
Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $117,684.00
Amount approved by CO on 8/11/98 $7,000.00
Amount approved by CO on 9/14/98 $102,705.00
NYC-WTC_000168472