03/31/98- M0N,15:.35 FAX 2126458962 ■ I ‘ KABACK AMBASSADOR ®003
5. Ductwoik per Page 5:
a, 1 eketcher, 1/4 hour at $98.00/hr. $ 24.50
b. 1 shop fabricator, 7 hours at
$96.00/hr. 686.00 ^^1^
c. 2 field men, 3 1/2 hours each at
$96.00/hr. 784.00
d. Material 12 0.00/^
SUBTOTAL $ 1,590.00 !A^-5
10% Overhead 159.00
10% Profit 174.90 .
$ 1,923.90
X 32 Locations „
TOTAL $61,564.80
7. The cos: for 88 Ruskin Model #CD80AF4
hurricaie dampers with 45" W.G. static
pressur 2 $64,800.00
8. The cos; for the 32 architectural
10x10 grilles $ 4,800.00
TOTAL $207,656.00
9. Less - Amount included, in base contract ($40,000.00)
TOTAL. $167,556.00
10. The add alternate for Valvcon electric
2 posit .on, 12 0 volt industrial actuators
In Duct’/ork $37,000.00
In. Hurr.cane Wall 52,000.00
TOTAL $89,000.00
Please be aivised that the hurricane dampers have a 7 week lead
time from tlie date of order.
If you have any questions regarding the above, please feel free to
contact me,
Very truly yours,
KABACK ENTERPRISES, INC.
It Donald M. Mur
Vice President
DMM/maw