AIA DOCUMENT G 701 CONTRACTOR X
FIELD
OTHER
PROJECT: 890094-0300 CHANGE ORDER NUMBER: 30
Mayor's Office of Emergency Management
TO (Contractor)
ARCHITECTS PROJECT NO.
Ambassador Construction Company CONTRACT FOR: 7 World Trade Center
317 Madison Avenue
New York, New York
10017 CONTRACT DATE: 04/17/00
Ambassador Change Order #113 ....... $ 3,253.00
Remove existing fire rated hatch at T' floor tank room, and to furnish and install an new 2'6"X2'5"
'FR-2" hour rated hatch by Bilco that will be custom fabricated to be selfclosing when inergen
system is activated. General contractor is verify all dimensions and use existing opening and
framing.
TOTAL COST FOR ABOVE SCOPE: $3,253.00___________________
The original Contract Sum was........................................................ .......... $11,533,019.00
Net change by previous Change Orders.................................................... $ 1,267,480.00
The Contract Sum prior to this Change Order was.................................... $12,814,444.00
The Contract Sum will be (increased) by this Change Order.................... $ 3,253.00
The new Contract Sum including this Change Order will be................... $12,817,697.00
The Contract Time will be (unchanged) by ( )days
The Date of Completion as of the date of this Change Order therefore is
Silverstein Properties, Inc, as Managing
Ambassador Construction Agents for 7 World Trade Company
Architect Contractor Owner
317 Madison Avenue
New York, NY 10017 Fifth Ave.. NYC, NY 10175
Address Address Address
BY BY BY
DATE DATE BY
NYC-WTC_000171501
OCR can misread numbers and units. Confirm readings against the page image before using them.