The Contractor shall attend meetings or conference calls with EPA and coordinate field activities, as
requested. •
All appropriate data, original field foms/data sheets, and chain-of-custody forms shall be completed in
accordance with the instructions contained in the contract and provided to EPA. All samples and copies
ofnecessary documentation shall be hand delivered to EMSL laboratories at: 307 W. 3 8* St., New York,
New York 212-290-0051. This information may also be provided via FormsII Lite (F2L) or an
alternative electronic format that is accessible by the laboratory.
Deliverables
All deliverables shall be provided via F2L or an agreed upon alternative electronic format approved by
USEPA and DEP.
The Proj ect Monitor shall also maintain a copy of each deliverable and al 1 filed documentation submitted
under this contract for 365 days.
The Project Monitor shairdirectand Goordinate all services and report all findings to EPA. The<scope of
this project will be as follows: ■
1. The Project Monitor shall be responsible for accessing a secure EPA Website (url, user name and
password to be provided by EPA) toobtal n requestor information (address, building identification
numbers, etc.). In coordination with the EPA. the I’rojectMonitorwill access residential services
requested from the Website and schedule clean-up activities and air sampling with the
tenants/owners, asbestos abatement contractors and air monitoring technicians for the various
apartments. The Project Monitor will then supply relevant information on activities for the EPA
Indoor Air database via the secure EPA website. Data to be input may include but is not limited
to start and completion dates for the cleaning, sampling dates and sample identification numbers.
Deliverable
The Project Monitor shallreview aUdeliyerabies prior to submission to EPA. The review shall
assure that each deliverable is accurate and complete, technically sound, and free ofclerical errors.
The Project Monitor shall provide a validated address and scheduling information into the EPA
Indoor Air web database via F2L or an agreed upon alternative electronic format or website
approved by EPA within 24 hours of activity.
2. The Project Monitor will schedule and conduct pre-cleaning or pre-sampling building inspections