114 Liberty - Revised Proposal
2.) As a continuation of the demolition phase setup, continue the
Reinoval of all spray on fire proofing from all deck and beams
and perform all required cleanups on all 12 floors via full
containment procedure in accordance with NYC DEP Regulations
etc.. and all disposal of such items as asbestos waste.
- All spray-on fireproofing on deck & beams appx. 3,500 sf
- All associated required cleanups, disposal as ACM and break
down for each floor.
Trio Asbestos Removal Corp, will provide all insurance, labor,
materials, equipment and disposal to perform all spray on asbestos
removal' and all related activities for the total sum of :
Hine Hundred Eighty Thousand Dollars fi 00/100 C.
($ 980,000-00 ).
Inoluded la the price axe the following ;
1.) An AIG Insurance producer with two Million and Five Million
Umbrella occurrence form best rated A+ 15 Insurance.
2.) All filing fees and permits.
3.) All asbestos waste will be disposed of at an EPA approved
hazardous waste site. An original waste manifest will be
provided to owner.