ITRI^ ASBESTOS REMOVAL CORP.
t: S I 19 Ei 7
14-20 I29th Street
December 27, 2002
Re : 1X4: Liberty
Dear Mr. Warnick:
Following is Trio's revised proposal to perform the required work
under two separate scope of work a follows :
1.) Install all plastic protection and perform on all 12 floors,
all interior demolition of all ceiling systems, walls, floors,
HVAC via full containment procedure in accordance with NYC DEP
Regulations etc., and all disposal of such items as asbestos
waiste.
“All sheet rock drop ceiling system appx. 5,500 sf
-All HVAC duct system appx- 2,500 sf
“ All interior & perimeter sheet rock Partitions appx. 8,000 sf
with insulation.
- All Parka wood flooring system appx. 5,500 sf
Trio Asbestos Removal Corp, will provide all Insurance, labor,
materials, equipment and disposal to perform all asbestos removal
and all related activities for the total sum of :
One Million Sevan Bnndsed Righty Thousand Dollars & 00/100 C.
($ 1,780,000.00 ).