Inspections conducted on September 25,2001 - Carlstien Lutchmedial
100 Church Street -Pecunies, Rogak and myself met the Chief Engineer. He said that they were
still taking bids for the job. We inspected the 2"** floor and observed that it was in they same
condition as last week. He did not know when the clean up would start.
40 Rector Street - Met with Joe Kelleher. He said that the building was without power because
Con Ed was in the process of converting from temporary power to permanent power. This would
take all day. Inspection of some of the floors revealed that there was no power. I also spoke to
Scott Furman the attorney for the building. He said that they have done TEM’s on the lobby.
Id”*, and 18“* floors. However, by Friday 28“*, 2001 they should have completed TEM
throughout the entire building. We also discussed the tracking of debris into the lobby. Furman
agreed to place a heavy duty industrial carpet so that tracked debris will be removed from
footwear.
4 World Financial Center- met with John Martens of Merrill Lynch Corporate services (212)
449-0370, He said that Pinnacle was hired to do the clean up and Weston to do air monitoring.
No one was working at this time.
3 World Financial Center - Met with Joe Fontana the security manager. He said that the got a
positive sample on the 23 floor. The other floors were negative. However, they were still doing
more test. I later met with Mike Foley the environmental manager (212) 972 -0651.
2 World Financial Center - met with Wojciech Olsewski # 80793 a handler supervisor. At this
time they were cleaning the lobby of the building. This had been requested by DOH because of
the large amounts of rotted food that was in the cafeteria. GPS was the 3*^ party air monitor on
site.
90 West Street - all windows blown out. Building is unoccupied.
85 West Street - Marriott Hotel at this time LVI’s, Judy A. Gilbert was on site with the Building
Manager. They have planed for now, to start the clean up tomorrow. The entire building is
scheduled to be cleaned as ACM contaminated. At this time they building was vacated and had
no power.
53 Park Place - only a security guard was at the front desk. He was given information to pass on
to management.
75 West Street - Building with major damage. Abandoned at this time.
99 Washington St. - This a parking lot with 70 cars at this time. There is heavy debris
accumulations on every surface. The manager Juan Acevedo and another employee were
washing the cars at this time. They are not asbestos workers. This work is being done as a regular
■car-wash operation. — ------ ---------
30 West Broadway - building has some structural damage. No one in building at this time.