I 12119101@ 9:00 AM
THERE WILL BE A MODIFICATION IN THE SITE LOGISTICS PLAN AND THERE WILL ALSO BE A REVISION OF THE
EMERGENCY EVACUATION PLAN. SIRENS HAVE BEEN INSTALLED AND FINALIZED MODIFICATIONS TO BE FD/DDC OPEN
12
RELEASED ON FRIDAY 12/21.
DUST SUPPRESSION EFFORTS NEED TO BE IMPROVED. 4 PRIMES OPEN
13
DEP REQUESTED FDNY WEST COMMAND BE RELOCATED TO GAIN ACCESS TO THE TIDE GATE. PROPOSED
LOCATION, IS THE TRUCK R.1,,IP. PAPD HAS NO PROBLEM WITH THIS LOCATION, AWAITING APPROVAL OF DDC OPEN
14
THE FDNY. (Ino1// ' Y v ,-`i';ei c 4/ S cd~c( /,6i.-
ALL UTILITY WORK TO BE PERFORMED WITH IN RED ZONE MUST HAVE DDC WRITTEN APPROVAL FROM CON-ED/VERIZON OPEN
15 LOUIE RUEDA
PARKING RESTRICTIONS HAVE GONE INTO AFFECT ON WEST STREET. OEM/DDC TO.EVALUATE POSSIBLE OEM/DDC OPEN
16 PARKING SOLUTIONS. UPDATE NEXT WEEK.
1~ DDC IS EVALUATING CONSOLIDATION PLAN FOR CM'S. BOVIS AND AMEC WILL BE TAKING THE LEAD. DDC OPEN
SHOULD BE WORKED OUT BE THE END OF DECEMBER.
ANY SUB-GRADE ENTRIES INCLUDING UTILITY ,WORK HAVE TO BE REPORTED TO BOB ADAMS AND THE FIRE
18N EPARTMENT.
DC OPEN
ROAD PLATING NEEDS TO BE PINNED DOWN BEFORE THE SNOW STARTS. SIGNS SHOULD ALSO BE PLACED ON-ED/VERIZON OPEN
19 AROUND THEM. DDC TO REVIEW WHERE WORK IS STILL REQUIRED.
TULLY OPEN
20 LIBERTY STREET PEDESTRIAN ACCESS PATH TO BE IMPLEMENTED BY TULLY.
OPEN
2 DOT TRUCKS WILL BE USED. MORE DETAILS TO FOLLOW.
PRIMES OPEN
22 STEEL ON FLAT BEDS MUST BE TIED DOWN WHEN COMING OUT OF THE HOLE.
PRIMES OPEN
23 EACH PRIME SHOULD LOOK AT THEIR SCAFFOLD STATION AND MAKE SURE THAT THEY ARE SECURE.
TEST RUN OF BUSES DOWN CHURCH STREET HAS OCCURRED. P RMANE BUS SERVICE MIGHT BEGIN OEM/DDC OPEN
24 NEXT WEDNESDAY, 12/26.
WEEKS OPEN
25 WEEKS REPORTED NUMBER OF BARGES ARE PRESENTLY ADEQUATE.
PRIMES OPEN
26 WE ADVISE WORKERS THAT WE ARE STILL IN COMPLIANCE WITH OSHA.
NYC-WTC 000154551