Sample results will require assessment for the purpose of developing background levels. These
results and their interpretation will have to be transmitted to residents and building owners who
participated in the study.
Prepare a final report which summarizes the study and presents the rationale used to establish
background levels for the various potential contaminants of potential concern.
Expected Completion Date:
Given the voluntary nature of the Background Study it took longer than originally projected to
obtain access to the number of buildings we identified. This will also result in a delay in the
completion of this study, the lAG completion date will still require an extension. EPA assumed
the access responsibilities from the NYCDOH. This change resulted in an increase in EPA
personnel costs. The change in projected completion date and cost changes are reflected in an
lAG amendment which is presently circulating.
The revised project completion date has been estimated to be April 30, 2003.
Complex Issues Encountered:
None to date.
Cost Summary: (as of 10/31/02)
(costs presented below include those reflected in the LAG amendment that is presently in
circulation)
Budget Category Funds Authorized Funds Expended Balance
Personnel $317,814 $ 52,997 $ 264,817
Travel $ 15,630 $ 10,879 $4,751
other $950 $220 $730
Sampling Contract $ 145,600 $ 68,255 $ 77,375
Analytical Lab Contract $ 705,300 $331,800 $373,500
Equipment $ 130,000 $850.00 $ 129,150
Data Validation $ 58,800 $25,1 •ZE $ 33,800
Contract
Totals $1,374,094 $489,971 $884,123
NYC-WTC_000147988