NYC 9/11 Public Portal Document
3
Following the receipt and validation of results, data will be incorporated into our existing
database.
Data will be evaluated relative to cleaning techniques used, compared to health benchmarks and
summarized in a final report. The evaluation of these data will also be required for the issuance of
a clearance letter which will be issued to the owner of 110 Liberty.
Expected Completion Date:
All field activities ended on October 25,2002. We expect that this will conclude all field work
but are awaiting the final testing results.
We estimate that a final report will be completed by January 30,2003.
Complex Issues Encountered:
The use of an aggressive sampling protocol to collect air samples required program adjustments
and will be assessed in the final report. Samples were collected at various flow rates and volumes
in an effort to provide the data necessary to perform this evaluation.
Cost Summary: (as of 10/31/02)
Budget Category Funds Authorized Funds Expended Balance
Personnel $ 462,234 $ 97,260 $ 364,973
Travel $ 32,766 $ 3,294 $ 29,471
Equipment $ 130,000 $ 59,028 $ 70,971
RST Contract $ 462,000 $ 275,1JBE $ 187,BEE
ERS Contract $ 790,500 $ 540,395 $ 250,105
Analytical Laboratory $2,512,iBEE $ 575, SEE $1,937,1SEE
Services Contracts
Totals $4,389,500 $1,549,977 $2,839,520