NYC Department of Health, the U.S. EPA, the DEP, and other agencies or entities with
jurisdiction monitor health risks in the aftermath of the WTC disaster. It has been
recognized that children are generally more vulnerable to most health hazards than the
general population. In order to have school-age children avoid unnecessary exposure to
health hazards, schools in and around the World Trade Center site were closed off to the
public until they could be tested for presence of asbestos and other toxicants. Residential
areas were also cordoned off, including most of Battery Park City.
While excavation continues at the site, the Health Department has been monitoring the air
quality and the U.S. EPA and the New York City Department of Environmental
Protection (DEP) are also conducting tests. The Health Department has produced a
Public Health Advisory for residents and people returning to work in the nearby area.
Residents and workers are advised to guard against dust and soot that can cause
respiratory symptoms and eye and throat irritation. Residents in the immediate area are
advised to keep windows closed and to avoid strenuous outdoor activity in the area
affected.
Environmental Impacts
Construction contractors rebuilding the WTC site will conform to OSHA health and
safety requirements such as described by the OSHA Guidance Manualfor Hazardous
Waste Site Activities (NIOSH 1985) and Standard Operating Safety Guides (U.S. EPA
1992b). Health and safety plans will be developed and will include environmental and
exposure monitoring. Contractors will maintain compliance with all environmental
regulations and permits that apply to the work being performed. Periodic environmental
health and safety monitoring may need to be performed to verify that employees are
protected and exposure limits are not exceeded. Each contractor working at the site will
maintain an OSHA 200 log. Pollution source reduction techniques and prevention
strategies, as appropriate, recommended by the U.S. EPA’s Office of Pollution
Prevention will be incorporated into the design of the proposed projects. If imexpected
conditions are encountered during excavation, for example, work will stop and the
appropriate actions will be taken.
To mitigate for any potential impacts associated with future construction, and to protect
human health and the environment, the following general actions will be performed:
• All materials (hazardous and non-hazardous) and wastes generated from
construction activities will be handled, stored and disposed of in accordance with
applicable Federal, state and local regulations
• Strict contract specifications will be established for construction contractors
requiring proper management and disposal of materials and waste
• Waste generation will be minimized to the extent possible
• Excavated soils and materials will be used as fill material, as appropriate