Part III — Health & Safety Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 3, August 29, 2005
National Institute of Occupational Safety and Health (NIOSH); the United States Environmental
Protection Agency (USEPA); the New York State Department of Conservation (NYSDEC); the
State of New York, New York State Department of Labor (NYSDOL); the New York City
Department of Environmental Protection (NYCDEP); and the City of New York.
This document incorporates relevant health and safety guidance developed for the Lower
Manhattan Development Corporation's 130 Liberty Street building Deconstruct Project as
described in their May 2005 Health and Safety Plan for that project.
Compliance with this HASP is required due to hazards associated with the Buildings' current
condition and anticipated Abatement Phase activities. This HASP is based upon current
knowledge of conditions at the Site and will be updated as new information (including personal
and environmental sampling and field observations) becomes available and/or conditions change
within the Building.
2.0 HEALTH AND SAFETY PROCEDURES
This section identifies the principal hazards associated with the tasks to be performed during the
cleaning, asbestos and COPC abatement, and interior component removal and conventional
demolition activities, and establishes standard safety and health procedures for the Contractor,
the Subcontractors and anyone who comes onto the site. The content of this HASP is designed to
anticipate, identify, evaluate, and control safety and health hazards for the work activities to be
performed during this project. All on-site work activities by any Subcontractors and their
designees shall be performed in accordance with this HASP, and in accordance with applicable
federal, state, and local regulations.
The levels of personal protection and the procedures specified in this Plan are based on the best
information available from validated reference sources (i.e., OSHA, NIOSH) and current site
data. Therefore, the guidelines presented in this HASP represent the minimum health and safety
requirements to be observed by all on-site personnel engaged in this project. Discovery of
currently unknown site conditions or changes in the scope of work will necessitate the
reassessment of the protection levels, controls, and procedures stated herein. All amendments to
this HASP must be made in consultation with the Regulatory Agencies, and must have prior
written approval by the Environmental Consultant's Certified Industrial Hygienist (CIH) and the
Contractor's Project Manager.
2.1 PERSONNEL RESPONSIBILITIES
The Contractor, Subcontractor and other personnel on-site shall review and understand this
document prior to working on-site.
All personnel shall:
6
NYC-WTC 000134273
OCR can misread numbers and units. Confirm readings against the page image before using them.