NYC 9/11 Public Portal Document
• Use and maintenance of PPE
• Evacuation routes;
• Warning signals;
• Maintaining line-of-sight and communications;
• Rehearsal of scheduled activities;
• Hospital routes;
• Locations of safety equipment;
• Previous violations of the safety plan and procedures or changes to the program to
correct the violation;
• Anticipated hazards for the day's work activities;
• Any changes to the requirements for levels of PPE;
• The locations of work zones; and
• General site conditions.
All safety meetings shall be documented in the site H&S logbook. Meeting participants
shall sign an attendance sheet.
All personnel directly involved in the project site activities shall be trained for the tasks
they will perform, as required by applicable federal/state/local regulations. Refresher
training will be performed at least yearly. In addition, all site personnel shall participate
in site-specific training and participation of personnel in training shall be documented,
. with proof of training maintained on-site. The topics of training required are dependent
on the SOW. This training shall be administrated by the Contractor, the Subcontractor, or
certified training facilities.
2.9.1 Health and Safety Awareness Training
Each Subcontractor shall be responsible for presenting and discussing the elements of this
HASP with their personnel and subcontractors, and ensuring that personnel follow the
elements of this HASP when working on-site. Prior to the start of work activities, or
whenever a new hazard is introduced into the work area, employees shall be provided
with the information indicated below. The Contractor or HASP CIH shall be available to
address any questions or assist in the presentation of the HASP information to project
employees. Information to be addressed during this training shall include, but not be
limited to:
• Hazardous chemicals present at the work site and their associated health risks.
• Potential physical hazards associated with the work activities, and proper safety
practices.
• Proper use of all tools and equipment to complete the scope of work activities.
• Requirements of the site Hazard Communication Program, including the labeling
of containers.
• Site alarm system, emergency response procedures, and location of emergency lay
• down Area.
The Copper Group —133-135 Greenwich Street & 21-23 Thames Street
Airtek Project 05=0710 - Phase I HASP 6-8-05 Page 29 of 40
NYC-WTC 000127766
OCR can misread numbers and units. Confirm readings against the page image before using them.