130 Cedar Street July 15, 2004
Selective Demolition and Façade Restoration Koenen Associates
Corrections Noted" or "In General Conformance With Design
Concept Except As Noted", provided such action will expedite
construction and noted corrections are adhered to. If fabrication is
not made strictly in accordance with corrections noted, the Item
shall be rejected in the field, and the Contractor will be required to
replace such work In accordance with corrected submittals.
10. Submittals marked "Revise and Resubmit" or "Rejected":
a. When submittals are contrary to contract requirements or too many
corrections are required, they shall be marked "Revise and
Resubmit" or "Rejected". No work shall be fabricated under this
mark. The Architect shall list his reasons for rejection on the
submittals or In the transmittal letter accompanying their return.
The submittals must be corrected and resubmitted for approval.
11. All shop drawing and samples shall be identified as follows.
a. Date of submittal.
b. Title of project.
c. Name of Contractor and date of his approval.
d. Name of subcontractor or supplier and date of submittal to Contractor.
e. Number of submission.
f. Any qualification, departure, or deviation from the requirements of the
Contract.
g. Federal Specification or ASTM number where required.
h. Such additional information as may be required by the Specifications for
the particular material being furnished.
12. If the Contractor wishes to deviate from the materials or details as shown in
Specifications or Drawings, he shall submit the proposed deviation with shop •
drawings and/or samples stating the extent and the materials or details being
replaced. The Contractor shall also submit information on the allowed credit or extra
cost required for the proposed deviation, and also all information relating to the work
of other Sections revised by the proposed deviation.
13. The Architect will review and approve shop drawings and samples for approval
with reasonable promptness, but only for conformance with the design concept of
the work and with information, contained in the Contract Documents.
14. Incomplete shop drawings will be returned without checking for proper
submission, and this shall not be considered as cause for delay of the work or
extra compensation to the Contractor.
15. The Contractor shall submit appropriate transmittal forms with every submittal of
Shop drawings, manufacturer's literature, and samples. All sepia reproducibles
shall be rolled on cardboard tubes for resubmia. The Contractor shall submit all
required shop drawings, manufacturer's literature and samples in accordance
with the procedures outlined below.
16. Unless otherwise specifically directed by the Architect, make shop drawings
al l
accurately to a scale sufficiently large to show all pertinent features of the item
and Its method of connection to the work.
•
Submittals 01300-3
NYC-WTC 000125120