130 Cedar Street July 15, 2004
Selective Demolition and Façade Restoration Koenen Associates
4. Shop drawings for each Section of the work shall be numbered consecutively,
and the numbering system shall be retained throughout all revisions. Each
drawings shall have a clear space for the stamps of the Contractor, Architect,
S and one of the Architect's consultants.
5. All shop drawings shall be thoroughly checked by the Contractor for compliance
with the Contract Documents before submitting them to the Architect and shall
bear the Contractor's stamp of acoroval certifying that they have been so
checked. Any shop drawings submitted without this stamp of approval and
certification, and shop drawings which, In the Architect's opinion, are incomplete,
contains errors or have not been checked, or only checked superficially, will be
returned unchecked by the Architect for re-submission by the Contractor.
6. In checking shop drawings, the Contractor shall verify all dimensions and field
conditions and shall check and coordinate the shop drawings of any Section or
trade with the requirements of all other Sections or trades whose work is related
thereto, as required for proper and complete installation of the work. The
Architect will review shop drawings. The Architect's acceptance of shop
drawings is for design only and not method of assembly or erection. Acceptance
shall in no way be construed as (1) permitting any departure whatsoever from the
Contract Documents; (2) relieving the Contractor of full responsibility for any error
in details, dimensions, omissions, or otherwise that may exist; (3) relieving the
Contractor of full responsibility for adequate field connections, erection
techniques, bracing, or deficiencies in strength; (4) relieving the Contractor of full
responsibility for satisfactory performance of all work and coordination with the
work of all subcontractors and other contractors; or (5) permitting departure from
additional details or Instructions previously furnished by the Architect.
Acceptance of such drawings shall not be construed as a complete check, nor
shall it relieve the Contractor from responsibility for proper fitting of the work, nor
from the necessity of furnishing any work which may not be indicated on shop
drawings when approved. The Contractor shall be solely responsible for any
quantities which may be shown on the shop drawings.
7. No work shall be fabricated, manufactured, or installed from shop drawings
stamped "Revise and Resubmit" or "Rejected", and such shop drawings shall be
corrected and resubmitted by the Contractor until accepted by the Architect. At
least one complete set of "No Exceptions Taken", Make Correction Noted" or "In
General Conformance With Design Concept", "In General Conformance With
Design Concept Except As Noted" shop drawings shall be kept at the site in the
contractor's field office for reference at all times. "Revise and Resubmit" or
"Rejected" shop drawings shall not be permitted at the site.
8. Submittals marked "No Exceptions Taken" or "In General Conformance With
Design Concept":
a. Submittals which require no corrections by the Architect will be
marked "No Exceptions Taken" or "In General Conformance With
Design Concept".
9. Submittals marked "Make Corrections", "Noted" or "in General Conformance With
Design Concept Except As Noted":
a. Submittals which require only a minor amount of correcting shall be
marked "Make Corrections Noted" or "In General Conformance
With Design Concept Except as Noted". This mark shall mean that
checking Is complete and all corrections are obvious without
ambiguity. Fabrication will be allowed on work marked "Make
•
Submittals 01300-2
NYC-WTC 000125119