130 Cedar Street July 15, 2004
Selective Demolition and Façade Restoration Koenen Associates
SECTION 01300
SUBMITTALS
•
PART 1.00 - GENERAL
1.01 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with the
requirements of the Contract Documents.
1.02 WORK INCLUDED
A. Work of this Section includes all labor, materials, equipment and services necessary to
complete submittal requirements as specified herein, including, but not limited to, the
following:
C-
1. Shop drawings and samples.
2. Manuals.
3. Integrated drawings.
1.03 RELATED WORK
A. Section 01600 — MATERIALS AND EQUIPMENT.
B. General submittal requirements - General Conditions.
PART 2.00 - PRODUCTS
2.01 SHOP DRAWINGS AND SAMPLES
A. General
1. The Contractor shall be responsible for coordinating the schedule for submittal of
shop drawings and samples with his progress schedule and the requirements of
the Contract Schedule, and submit a coordinated schedule of submission of all
shop drawings and samples to the Architect.
2. Failure of the Contractor to schedule and submit shop drawings and samples In
ample time for checking, correction, and rechecking will not justify any delay in
the Contract Schedule. Allow ample time for items to be tested, Including time
for retesting If the tests or mock-ups fail.
3. Samples, shop drawings, manufacturers' literature, and other required
Information shall be submitted In sufficient time to permit proper consideration
and action on same before any materials and items are delivered on the work.
Stagger submissions so that the Architect can review the documents in an orderly
and timely manner, All samples of materials requiring laboratory tests
shall be submitted to the laboratory for testing not less than 90 days before such
materials are required to be used in the work. All other samples, Manufacturers'
literature, and other sample information shall be submitted for approval not less
than 30 days before such materials are required to be used in the work.
..
Submittals 01300-1
NYC-WTC 000125118