NYC 9/11 Public Portal Document
Regulatory Submittal Part 1 —Work Plan
Fiterman Hall — 30 West Broadway, New York. New York
Airtek Project 05-0867 — January 10, 2006
controls will be the responsibility of the Contractor, and may include, but not be
limited to the following:
Wet suppression: The use of water and/or amended water
Site housekeeping via vacuuming/sweeping
Limitation of free-fall of demolition debris
Limitation of freefall during waste loading
Sealed and/or covered transport
The listed controls are intended as a guideline. It is the responsibility of the
Contractor to implement whatever engineering control is required (whether
above-listed or not) to prevent fugitive dust.
Failure to suppress dust that results in visible fugitive emissions from the site will
result in a work stoppage. Work will not be re-started until adequate corrective
measures have been implemented to the satisfaction of the Site Hygienist, and the
USEPA/Regulators. The procedures to be followed with regards to visible
emissions are specified in the ECAMP (Part II of the Submittal).
7.3 Scaffolding
In preparation for demolition and at a time when exterior facade focused wiping
and operable window panel cleaning is performed on floors higher than the first
floor, a code approved demolition scaffold, netting, sidewalk shed and
construction fence must be installed per the site logistics plan. All required
permits for sheds, scaffold, hoists, lane closings, etc. will be obtained and
renewed by the contractor. Scaffold ties to the building may not be fastened to
the brick veneer, but must be fastened to steel spandrels to achieve the required
anchoring strength and so as not to break the building containment envelope. Any
penetration through the ACM Spandrel Flashing must be conducted under a NYS
DOL Variance in strict accordance with the asbestos/CoPC control procedure
detailed in the structural engineer's Deconstruction and Scaffold Layout Plan. A
scaffold tie may be installed through the exterior facade to an area inside the
building under a NYS DOL Variance in strict accordance with the asbestos/CoPC
control procedures described in the structural engineer's Deconstruction and
Scaffold Layout Plan.
7.4 Site Protection:
The Contractor will be responsible for all temporary protection to any adjacent
buildings and/or lots. The Contractor will include roof top protection, sidewalk
bridges as required to perform this work.
The Contractor will maintain the project site, adjacent sidewalks and streets free
from debris and garbage, including daily sweeping of sidewalks for the duration
of the contractor's work.
13
NYC-WTC 000095756
OCR can misread numbers and units. Confirm readings against the page image before using them.