Regulatory Submittal Part I — Work Plan
Fiterman Hall — 30 West Broadway, New York, New York
Airtek Project 05-0867 — January 10, 2006
hazardous waste determinations and hazardous waste manifests will be retained
for a period of at least three years from the completion of the project.
7.7 Site Work:
The Contractor will perform proper dust control during any demolition or removal
work. The procedures to be followed with regards to visible emissions are
specified in the ECAMP.
The Contractor will comply with all federal and local laws regarding noise
control.
All work will be done by appropriately qualified labor. The Contractor will be
responsible for employing qualified tradesmen for the duration of the Contractor's
contract work on this project.
Once the building is demolished, the contractor will leave a clean site with the
required construction fence in place. Any rubble in the cellar is to be removed
and the cellar concrete slab is to be left broom clean. Foundation wall bracing is
to remain in place. All demolition scaffolding will be removed from the site.
All work is to be performed in accordance with the latest standards as established
by OSHA.