NYC 9/11 Public Portal Document
Regulatory Submittal Part 1 —Work Plan
Fiterman Hall — 30 West Broadway, New York, New York
Airtek Project 05-0867 — January 10, 2006
The Contractor will provide and maintain a plywood fence along all sides of the
property. All work to be coordinated with NYC Department of Buildings (NYC
DOB) temporary fence permit. Upon completion of the Contractor's work, the
fence and gates will be left in an acceptable condition, with gates in locations
approved by, and coordinated with, the General Contractor. General Contractor
will obtain fence permit(s) and maintain permit(s) for the duration of the project.
Fence will comply with NYC DOB requirements and will be constructed of
minimum 5/8" exterior grade plywood on two by four frames. Fence will be
painted Dark Blue and will have "Post No Bills" painted a maximum of 10 feet on
center. Fence will be constructed with wood or metal posts at regular intervals.
Post will be sunk into the ground as required to make them free standing without
bracing or outriggers. Fence will be constructed such that sections of it are easily
removable without disturbing remaining sections. Blind spots will not be created
on sidewalk.
7.5 Demolition Sequence:
Once the entire building is removed from containment, the contractor will
decommission the elevators, disconnect all utilities to the site, obtain a demolition
permit and remove the windows. If an outside hoist that has been used for
remediation is not left in place as a Fire Department readiness hoist or when the
contractor has decommissioned the interior elevators, the contractor will install an
outside Fire Department readiness hoist in the location designated on the site
logistics plan, with openings at floors as mandated by the FD. The hoist can be
used as a personnel hoist to get demolition workers to the upper floors. The
contractor will deconstruct the building in the sequence described in their work
plan, keeping dust to a minimum through the use of water spray and tarps. As
each floor is deconstructed, material will be pushed down abandoned shafts and
dropped to the cellar level, where backhoes and loaders will move it onto trucks
parked on a ramp that runs from the cellar to street level on Greenwich Street.
The material will then be carted to waste sites or recycling plants.
7.6 Waste Management— Conventional Demolition:
Conventional demolition will involve only the remaining structural components
and masonry exterior of the building, and the non-friable asbestos spandrel
flashing. As detailed in the WMP (submittal Part IV), representative waste will be
collected by the Environmental, Consultant for analysis by Full TCLP and RCRA
characteristics. Based on the results of TCLP testing, the waste will be
characterized according to any RCRA exceedances. Disposal will be only to
facilities licensed to accept the waste so characterized.
Transportation and Disposal will be as described in Part IV of the Submittal,
"Waste Sampling & Management Plan" Sections 9, 10 & 11. Records of