Inspection Details:
As part of the survey, the Mechanical and the Environmental Professionals inspected the following HVAC system
types.
A. A total of eighteen (18) mechanical exhaust fans serving the kitchens and bathrooms located on the main roof
and one (1) passive shaft exhaust located on the main roof.
B. One (1) AC window unit located in the elevator room and serves the elevator room.
C. One (1) McQuay HV unit is located in the machine roof of the 1' fl behind the mailroom, serves the southeast
side of the hallways on the 2nd floor through the 9th floor. This unit has not been functioning for the last 15 years
according to Mr. Ray Perez (superintendent of the bldg).
D. One (1) McQuay HV unit is located on the main floor in the pump room serves the northwest side of the
hallways from 2"d floor to 9d' floor.
E. One (1) Skill Aire AC split unit is located in the pump room, serves the lobby.
F. One (1) AC unit is located in the room behind the mailroom and hanging from the ceiling, serves the vestibule
by the mailroom.
G. One (1) HV self-contained unit is located at the north entrance of the lobby serves the lobby.
H. One (1) HV self-contained unit is located at the south entrance of the lobby serves the lobby.
All identification data and visual inspections are documented in the attached checklists.
Summary of Findings:
The mechanical exhaust fans # 2,3,4,5,6,7,8,9,10,11,12,13,14,15,16,17,18 (as they are numbered in the evaluation
forms), and their associated components are covered with WTC related dust.
One (1) McQuay HV unit located on the main floor in the pump room. Heavy accumulation of WTC related dust was
observed in the system. A total of 100 linear feet of duct needs to be cleaned.
One (1) Skill Aire AC unit located in the pump room. WTC related dust found in the system. A total of 70 linear feet
of duct needs to be cleaned.
All the other systems inspected appear to be free of WTC dust,
All the findings are documented in the attached evaluation forms.
Scope of Work:
Clean the mechanical exhaust fans #2,3, 4, 5, 6, 7, 8, 9,10,11,12,13,14,15,16,17,18 (as they are numbered in
the evaluation forms), and their associated ducts. The fans are located on the main roof. A total of
approximately 2,000.00 linear feet of duct needs to be cleaned.
One (1) McQuay HV unit and its associated ducts. A total of 100 linear feet of duct needs to be cleaned.
One (1) Skill Aire ACunit and its associated ducts. A total of 70 linear feet of duct needs to be cleaned.
Please feel free to contact me should you require any further information.
Sincerely,
V ilis Be los
Directoro Operations
Attachments: 1) Ventilation System Evaluation forms
2) Maintenance activity reports
Page 2 of 2
NYC-WTC-000116171
OCR can misread numbers and units. Confirm readings against the page image before using them.