Asbestos Insnectlon Report
Premise No. Inspection Date:
114 Liberty Street March 8, 2003
Floor Zip Borough Block Lot Squad # Badge #
All 10006 1 (Manhattan) 52 7502 N/A A019
Inspector Building Type Basis of Inspection Photos Taken
Penny Theodorellys A WTC Unoccupied Bldg DEP Cleanup No
Contractor's Name Sample Number
ETS Construction, Inc N/A
Address City Sample Number
160 Clay Street, Brooklyn N/A
State Zip Phone Sample Number
NY 11222 (718) 706-1032 N/A
Laboratory Name Owner's Name
JLC Environmental Consultants 114 Liberty LLC
Address City Address City
200 Park Avenue South, New York
State Zip Phone State Zip Phone
NY 10003 (212)420-8119
Contact Person Time of Inspection from:
5:30 P.M. — 8:30 P.M.
This inspection was the continued monitoring of the DEP clean-up activities at the site. All work to be
performed in accordance with contracts WTC-LBC and WTC-LBA. Clarifications and updates were provided to
the contractors and residents by e-mail. Copies of correspondence to be Incorporated with these Inspection
reports.
Contractor and Project Monitor representatives were present on site at my arrival. The project monitor was Mr.
David Ezekwesili. The site supervisor was Mr. Peter Radomsky (S Cert # 82452). Mr, Radomsky was In the
work area at the time of my arrival and met me upon exiting the area. Two workers were outside the building
awaiting the delivery of the waste containers. Workers were as follows: Villacres H 82452, Choromanski H
86922, Nemeth H 84821, Valencia H, Bobola H 89291, Kimec S 85585, Naydanuk H 85004, Korzep H 83392,
Borkdwski H 86355, Cabrera H 87791, Bobola H 90338, Stavanskyy H 85657, Storozh H 84264, Arendac H
92066, Sanislo H 91447. This crew was slightly larger than the day shift. The contractor stated that the size of
the shifts would be larger tomorrow. Decon has six showers and two hot water heaters. Shift can Increase
significantly without a change In set up.
Work place preparation activities were In progress. Decons were operational. Areas around the decons were
being maintained by one of the workers. Waste containers were not delivered to the site yet. Drop off of the
containers was expected this evening.
Mr. Radomsky entered the work area with me. Polyethylene sheeting was installed on the floors and over the
kitchen cabinets on the 11th and 12th floors. The cleaning of the floors was In progress on the 9th and 10~'
floors. The negative air machines had been moved but had been placed at the Cedar (south) side of the
building. All the machines were therefore located in the two rear bedrooms. Mr. Radomsky agreed to move
two machines from each apartment above the 4th floor to the dining room and vent out the east side as had
been earlier decided. At the 4"' floor piggy backing to the east side would be necessary.
Work progress was in keeping with project timeframes.