SECTION 02082
collected for each containment:
Five (5) PCM samples - inside work area
Three (5) TEM samples - inside work area
Three (5) PCM samples - outside work area
Three (5) TEM samples - outside work area
All PCM and TEM results must satisfy the clearance criteria for reoccupancy.
d) When volumes greater than or equal to 1,199 liters for a 25 mm filter and/or
2799 liters for a 37 mm filter have been collected and all the TEM samples
inside the abatement area is less than 70 s/mm’ of filter, the abatement work shall
be considered complete without comparing the inside samples to the outside
samples.
e) Remove any visible accumulation of asbestos material and debris. HEPA-
vacuuming and wet cleaning shall be perfonned on all surfaces inside the work
area. All sealed drums, plastic bags, and equipment used in the work area shall
be removed from the work area.
f) Upon request of the Contractor the Construction Manager will perform a visual
inspection. Evidence of asbestos contamination identified during the inspection
will necessitate further cleaning as heretofore specified.
g) Remove first layer of plastic sheathing inside the work area. The isolation barrier
and decontamination facility shall remain in place and be utilized.
2. Step 2: Second Cleanup:
a) After the first cleaning the work area shall be vacated for 12 hours to allow fibers
to settle. All objects and surfaces in the work area shall be HEPA - vacuumed
and wet cleaned for a second cleaning.
b) A thin coat of lockdown encapsulant shall be applied to all plastic covered
surfaces in the work area.
c) When the encapsulant is dry, second layer of plastic sheets on the walls, ceiling
and floors shall be removed. Do not remove seals from doors, windows, critical
barriers or disconnect the negative pressure equipment.
3. Step 3: Reoccupancy Clearance:
a) Four hours after the second cleanup, all the surfaces in the work area shall be
HEPA - vacuumed and wet cleaned for a third cleaning. Upon the request of the
Contractor, final visual inspection for reoccupancy will be done by the
Construction Manager for the purpose of observing whether cleaned areas are free
of dust, dirt, and debris. Evidence of asbestos contamination identified during the
inspection will necessitate further cleaning as heretofore specified.