SECTION 02082
D. Coveralls: provide disposable full-body coveralls and disposable head covers. Require that they
be worn by all workers in the Work Area. Provide a sufficient number for all required changes
for all workers in the Work Area.
E. Boots: provide work boots with non-skid soles, and where required by OSHA, foot protection,
for all workers. Provide boots at no cost to workers. Paint uppers of all boots yellow with
waterproof enamel. Do not allow boots to be removed from the Work Area for any reason after
being contaminated with ACM and/or dust.
F. Hard Hats: provide hard hats as required by OSHA for all workers, and provide a minimum of
four spares for Inspectors, visitors, etc. Label all hats with same warning label as used on
disposal bags. RequLe hard hats to be worn at all times that work is in progress that may cause
potential head injury. Provide hard hats of the type with polyethylene strap suspension. Require
hats to remain in the Work Area throughout the work. Thoroughly clean and decontaminate and
bag hard hats prior to removing them from the Work Area at the end of the work.
G. Goggles: provide eye protection (goggles) as required by OSHA for all workers involved in any
activity that may potentially cause eye injury. Require them to be worn at all times during these
activities. Thoroughly clean and decontaminate goggles before removing them from the Work
Area.
H. Gloves: provide work gloves to all workers, of the type dictated by the Work and OSHA
Standards. Do not remove gloves from the Work Area. Dispose of as asbestos-contaminated
waste at the end of the work. Gloves shall be work at all times, except during Work Area
Preparation activities that do not disturb ACM.
I. Reusable footwear, hard hats and eye protection devices shall be left in the contaminated
Equipment Room until the end of the Asbestos Abatement Work.
J. Disposable protective clothing shall be discarded and disposed of as asbestos waste every time
the wearer exits from the workspace to the outside through the decontamination facility.
K. Respirators, disposable coveralls, headcovers and footcovers shall be provided by Contractor for
the Facilities Representative, Resident Engineer and any other authorized representative who
may inspect the Work Area. Provide two respirators and six respirator filter changes per day.
1.26 AIR MONITORING
Work Area air monitoring for the pre, during and post abatement (clearance testing) shall be
performed in accordance with the most stringent of the Federal, State and City of New York
Laws and Regulations and the latest amendments to these laws concerning the asbestos removal.
They shall be performed by a third party laboratory employed by the Construction Manager
under a separate Contract. The cost of this work is not included in the Bid.
Air Sampling and Analysis requirements under NYS DOL ICR 56 requires that the selected
methodology of sampling and analysis of asbestos be the same for all pre-abatement, abatement
and post-abatement monitoring, however whenever final air clearance is required, AHERA and
the New York State Education Department requires public school final air clearance be
performed and analyzed using the TEM method, as well as in nonpublic school asbestos projects.
02082-39
CITY_21 MCI 00_014563812
NYC-WTC_000454612