Asbestos Abatement
the Contractor must have on hand at the beginning of each work day, at least four
(4) masks each with two sets of fresh filters, for use by personnel who are
authorized to inspect the worksite. The Contractor shall check for proper fit of
the respirators of all City personnel authorized to enter the Work Area.
C. Asbestos handlers involved in tent procedures shall wear two (2)
disposable suits, including gloves, hood and footwear, and appropriate
respiratory equipment. All street clothes shall be removed and stored in a
clean room within the work site.. The double layer personal protective
equipment shall be used for installation of the tent and throughout the
procedure, if a decontamination unit (with shower and clean room) is
contiguous to the Work Area, only one (1) layer of disposable personal
protective equipment shall be required; in this case, prior to exiting the tent
the worker shall HEPA vacuum and wet clean the disposable suit.
1. The outer disposable suit (if 2 suits are worn) shall be removed and
remain in the tent upon exiting. Following the tent disposal and
work site clean up the workers shall immediately proceed to a
shower a the work site. The inner disposal unit and respirator shall
be removed in the shower after appropriate wetting. The disposal
clothing shall be disposed of as asbestos-containing waste
material. The workers shall then fully and vigorously shower with
supplied liquid bath soap, shampoo, and clean dry towels.
D. Coveralls: provide disposable full-body coveralls and disposable head
covers. Require that they be worn by all workers in the Work Area. Provide
a sufficient number for all required changes for all workers in the Work
Area.
E. Boots: provide work boots with non-skid soles, and where required by
OSHA, foot protection, for all workers. Provide boots at no cost to workers.
Paint uppers of all boots yellow with waterproof enamel. Do not allow
boots to be removed from the Work Area for any reason after being
contaminated with ACM and/or dust.
F. Hard Hats: provide hard hats as required by OSHA for all workers, and
provide a minimum of four spares for Inspectors, visitors, etc. Label all
hats with same warning label as used on disposal bags. Require hard hats
to be worn at all times that work is in progress that may cause potential
head injury. Provide hard hats of the type with polyethylene strap
suspension. Require hats to remain in the Work Area throughout the work.
Thoroughly clean and decontaminate and bag hard hats prior to removing
them from the Work Area at the end of the work.
G. Goggles: provide eye protection (goggles) as required by OSHA for all
workers involved in any activity that may potentially cause eye injury.
CAPITAL PROJECT NUMBER PO79201K 02081-37
100: CONTRACT DOCUMENTS REV. May 3,2000
- 37 -100% CONTRACT DOCUMENTS