agents must fill the wet portion of a hole before the free-running ANFO
is loaded.
(2) Cartridged explosives are decked or threaded on a detonating
cord down line and each cartridge is initiated by direct contact with the
down line or by blasting caps. Presplit charges (para 5-4a) are string
loaded or joined continuously in special long cartridges.
(3) Powder factor is the widely used term for the pounds of explo
sive necessary to blast a cubic yard (or ton) of rock. This simple ratio
provides an approximation of the relative size of the charge in a hole or
those in a round.
5-3. General Rock Removal.
a. Bench Blasting. The most common method of production
blasting in quarrying and construction excavation is bench blasting. It
involves inclined, vertical, or horizontal blastholes drilled in single-
or multiple-row patterns to depths ranging from a few feet to 100 ft or
more depending on the desired bench height. Where the excavation is
shallow, i.e. less than about 20 ft in height, one level may suffice. In
deep excavations, a series of low benches, offset from level to level,
are recommended for operational convenience. Bench height is often
two to five times the burden and the ratio of burden to spacing is often
1:1.25 to 1:2.0.
(^) Spacing and Burden.
(a) High quarry benches are usually blasted with large-diameter
charges and large hole spacing. The rectangular array, with spacing
between the holes greater than the burden, is considered most effec
tive here. Common patterns for 5- to 6-1/2-in. holes in limestone are
14 by 20 ft (burden versus spacing) for 30- to 50-ft faces, and 16 by
24 ft for 50- to 70-ft faces.
(b) Lower benches, up to 40 ft, are commonly drilled with small
diameter holes (up to 4 in.), on a staggered or square delay pattern,
from 6 by 6 ft to 12 by 12 ft. Narrow low benches are often blasted in
a rectangular array of 4 by 10 ft to 6 by 9 ft depending on the rock
type, borehole diameter, and explosive density.
(c) Some blasters use a rule of thumb that the burden should be
between 20 and 40 times the drill-hole diameter.
(d) Another method of developing side and through cuts and
benches is the trapezoidal array^^ jn which holes fan out from bottom
5-4