B2-09. Care of Water.
c. Structure Area. The ground-water level shall be
lowered in advance of excavation to permit excavation in the
dry and to minimize the water in the pre split blast holes and
the presplit fracture. Not less than twenty days before the
rock excavation reaches elevation 770, calyx holes 1,2,
and 3 shall be thoroughly cleaned out and dewatering
started. The water level in the calyx holes shall be lowered
to and maintained at a level within 5 feet above the bottom of
the holes until excavation is completed. The Government
reserves the right to use the calyx holes for observations.
Calyx holes 1 and 3 shall be backfilled with lean concrete as
directed and calyx hole 2 shall be treated as shown on the
drawings. Lean concrete is specified in Division A, section
CONCRETE, GENERAL.
d. The Spillway-Powerhouse Area. Excavation
shall be performed in the dry.
B2-10. Blasting, a. General. All blasting in the spillway
powerhouse area outside of the structure area and in the
quarry for rockfill shall be designed to produce the maxi
mum amount of material suitable for rockfill zones and to
minimize the quantity of grizzly fines. No,blasting shall be
allowed within 100 feet of concrete or grout which has an
age less than 7 days nor within 50 feet of any concrete or
grout regardless of age. It was found in blasting for rock-
fill in quarry No. 2 during Stage I Construction that the use
of low density powder produced the best results, as the
quantity of grizzly fines was substantially reduced. As
“Special Surfaces,’’ “Bearing Surfaces,’’ other presplit
surfaces, and other final surfaces are approached, blasting
shall be carefully controlled to avoid damage to these sur
faces. Initial drilling and blasting in any area or type of
rock shall be limited to a maximum production of 2,000
cubic yards per shot until the method is proven to produce
the specified results. Subsequent drilling and blasting in
required excavations shall be limited to a maximum produc
tion of 6,000 cubic yards per shot in the Spillway Power
house Structure Area. In “Spillway-Powerhouse Excavation
- Rock*’ and “Quarry Excavation-Rock’’ the size of the shot
may be increased in increments up to 3,000 cu. yds. pro
vided the fragmentation and clay content of the excavated
material is and continues to be satisfactory. The maximum
B-6