CHAPTER 8. DRILLING AND BLASTING IN ROCK
EXCAVATION BY CONTRACT
8-1. General. The CE designs and supervises excavation projects
necessitating drilling and blasting by contractor forces. Many of these
excavations can tolerate only minimal blast effects on the rock mass
immediately adjacent to the lines and grades. Such excavations are
designed to be economical and yet to meet certain design criteria of
the final installation. Elsewhere, the Government has an interest in
fragmentation obtained in blasting rock, intended to be utilized for rock-
fill embankments and slope protection. Successful economical com
pletion can be accomplished, but it usually demands considerable effort
in planning, design, and inspection.
a. Customary Contract Approach. It is customary in construc
tion contracts that unit bid prices for the items “rock excavation,"
or in some cases “excavation unclassified," include all costs of drill
ing and blasting. If the rock outlining the excavation is to be protected,
it is common practice to describe the results required of the excava
tion operation by statements in the specification to the effect that;
(1) the explosives used shall be of such quality and power and shall be
used in such locations as will neither open joints nor crack or damage
the rock outside the prescribed limit of excavation, (2) as the excava
tion reaches final lines and grades, the depth of holes for blasting and
the amount of explosives used .per hole shall be progressively reduced,
and (3) excavation that exceeds the prescribed tolerance of lines and
grades will be backfilled with prescribed materials. Other restrictions
or limitations may also be included. It is the responsibility of the con
tractor to select the methods and operate in a manner that will pro
duce the required results. It is expected that a prudent contractor will
include in his bid a contingency item based on his judgment of the
difficulty of the required work. Some specifications go further and
prescribe routine procedures such as presplitting. The degree of
responsibility of the contractor for the success of these procedures
depends to some extent on the latitude and options given the contractor
in the manner of employing the procedures. This general industry
wide approach to rock excavation in contracts meets with varying
degrees of success. Where the rock excavation required is essen
tially the removal of large quantities of rock exemplified by highway
cuts, the unit price of rock excavation has remained relatively stable
over the last decade. However, when rock excavation requiring more
exacting results is considered, disputes and controversies are com
mon and may lead to claims for additional cost.
b. considered to be to the
best interest of the Government to reduce the element of risk for the
8-1