A meeting was held today (02/07/02) at 110 Livingston Street attended by representatives from
the BOE, SCA, UFT, M833 PA Consultant and ATC to review and finalize the scope of work for
the plenum cleaning at the High School of Economics and Finance. Below please find the final
scope of work as agreed to by the attendees.
SCOPE OF WORK
• Contractor will remove and replace with NEW all existing ceiling tiles from suspended
ceiling systems on the first through tenth floors. These tiles will be disposed of by the
Contractor as conventional waste. Following the removal of the ceiling tiles and prior to
the installation of new tiles, the Contractor will perform cleaning above the ceilings and
within the plenums to remove any visible debris and remove/repair any damaged/loose
duct insulation.
• The elevators shafts/pits and air return shaft shall also be cleaned. Cleaning shall be
performed utilizing wet wiping/HEPA vacuuming techniques in order to minimize the
migration of dust within the building.
• In areas where ceiling plaster and/or sheetrock, ceilings exist, the Contractor shall cut
access hatches in various locations within each space so as to allow for access above
these ceilings for cleaning purposes. Contractor will install new access hatches where
applicable on that floor.
• All other surfaces within the building including but not limited to lights, diffusers, floors,
walls, desks, chairs, window sills, etc. shall be protected during this work and shall be
rendered free of any dust and/or debris following the cleaning and prior to air sampling.