Part II - Environmental Community Monitoring Plan
133-135 Greenwich & 21-23 Thames Streets
Airtek Project 05-0701 - Rev 2 September 16, 2005
Appendix A
Measurement Quality Objectives for PM 10 and PM2.5 - [Ref. Quality Assurance Handbook for
Air Pollution Measurement Systems, Volume 11: Part 1, Appendix No: 3,1
Table A-1 - Measurement Quality Objectives - Parameter PM2.5
Requirement Frequency Acceptance Criteria 40 CFR
Reference
Filter Holding Times all filters < 30 days before sampling Part 50, .App.L
Pre-sampling < 10 days at 25 oC
Post-sampling weighing < 30 days at 4oC
Sampling Period All data 1380-1500 minutes Part 50, App.L Sec 3.3
or
value if < 1380 and
exceedance of NAAQS
Reporting Units All data g/ma Part 50.3
Detection Limit 2 g/tna Part 50, .App.L Sec 3.1
Lower DL .All data 200 g/ma Part 50, .App.L Sec 3.2
Upper Cone. Limit .All data
Filter
Visual defect check All Filters
Filter Conditioning Part 50, App.L Sec 6.0
Environment All Filters 4 hours minimum
Equilibration 20-23 C
Temp. Range +/-2‘’ C over 24 hr “ " Part 50, App.L Sec 8.2
Temp. Control 30% - 40% RH
Humidity Range +/- 5% RH over 24 hr.
Humidity Control
Lot Blanks 3 filters per lot less than 15 g
Lab QC Checks
Field Filter Blank +30 g change between Part 50, .App.L Sec 8.2
Lab Filter Blank 3 per weighing session weighings
Balance Check beginning, every 10th +15 g change between
samples, Sec. 7.9 weighings
end <3g
Duplicate Filter Weighing I per sample batch + 15 g change between
weighings
Calibration/Verification
Flow Rate (FR) Calibration If multi-point failure ± 2% of transfer standard ± Part 50, .App.L, Sec 9.2
FR multi-point verification 1/yr 2% of transfer standard ± Part 50, .App.L, Sec 9.2.5
One point FR verification 1/4 weeks 4% of transfer standard 80
External Leak Check every 5 sampling events mL/min Part 50, .App.L, Sec 7.4
Internal Leak Check every 5 sampling events 80 mL/min Part 50, .App.L, Sec 7.4
Temperature Calibration If multi-point failure + 2% of standard Part 50, .App.L, Sec 9.3
Temp multi-point verification on installation, tlien 1/yr ± 2 of standard Part 50, .App.L, Sec 9.3
One- point temp Verification 1/4 weeks ± 4E of standard Part 50, .App.L, Sec 9.3
Pressure Calibration on installation, then 1/yr 1/4 +10 mm Hg Part 50, .App.L, Sec 9.3
Pressure Verification weeks ±10 mm Hg Part 50, .App.L, Sec 9.3
Clock/timer Verification 1/4 weeks 1 min/mo Part 50, .App.L, Sec 7.4
Accuracy
FRM performance evaluation 1 ± 10% Part 58, .App A, Sec 3.5
Flow Rate Audit l/2wk (automated) ± 4% of audit standard
35
CITY_DEP_WORBY_CANNATA_SUBP_000087318
NYC-WTC_000425894