Asbestos Abatement
O. All asbestos-containing waste shall be transported from the abatement site to the
landfill by a registered Waste Hauler. When transporting ACW:
1. Ensure that the ACW has been sufficiently wetted down in a leak tight
container.
2. Re-wet and repackage any damaged containers.
3. Maintain at storage site an adequate supply of spare leak tight containers.
4. Maintain at storage site an adequate supply of amended water.
5. Keep ACW separate from any other waste.
P. Keep ACW in a secured, enclosed, and locked container.
Q- Waste transport documents shall conform to the requirements of the U.S.
Department of Transportation, Hazardous Materials Transportation Regulation,
49 CFR Part 173 and EPA 40 CFR 61.150 (d)(l)(2). Shipping documents shall be
clearly marked with the required designation "RQ Asbestos". Contractor shall
provide a copy of this document to the City.
R. A uniform hazardous waste manifest shall be prepared by the Contractor and
signed by the Contractor each time the Contractor ships a dumpster load of
Asbestos-Containing Waste Material. The uniform hazardous waste manifest shall
include the site of waste generation, the names and addresses of the Transporter,
the Contractor, and the landfill operator with information on the type and number
of asbestos-waste containers, time and date. Contractor shall provide the
consultant with signed copies of the waste manifest before each departure.
S. Contractor or his registered hazardous Waste Hauler shall transport asbestos
containing waste material from the abatement site directly to the specified
disposal site. Contractor or their Waste Hauler shall not accept material from any
other site when transporting asbestos-containing waste material from the
abatement site. The consultant reserves the right to travel with Contractor's Waste
Hauler to the waste disposal site. No intermediate storage of waste material (i.e.
Contractors warehouse) shall be permitted.
T. Final or progress application for payments will not be processed unless all
hazardous waste manifests generated to date have been received and reviewed by
the Resident Engineer.
U. All asbestos materials, wastes, shower water, polyethylene disposable equipment
and supplies shall be disposed of as contaminated waste, in accordance with the
EPA regulation (40 CFR, Section 61.150) and those requirements of the New
York State Department of Environmental Conservation and the New York
CAPITAL PROJECT NUMBER PO79201K 02081-88
100: CONTRACT DOCUMENTS REV. May 3,2000
- 88 -100% CONTRACT DOCUMENTS