SECTION 02082
HEPA-filters.
N. Contractor shall immediately clean debris or residue observed on containers or surfaces outside
of the Work Area. Cleaning shall be via HEPA equipped wet/dry vacuums only.
O. All asbestos-containing waste shall be transported from the abatement site to the landfill by a
registered Waste Hauler. When transporting ACW:
1. Ensure that the ACW has been sufficiently wetted down in a leak tight container.
2. Re-wet and repackage any damaged containers.
3. Maintain at storage site an adequate supply of spare leak tight containers.
4. Maintain at storage site an adequate supply of amended water.
5. Keep ACW separate from any other waste.
P. Keep ACW in a secured, enclosed, and locked container.
Q Waste transport documents shall conform to the requirements of the U.S. Department of
Transportation, Hazardous Materials Transportation Regulation, 49 CFR Part 173 and EPA 40
CFR 61.150 (d)(l)(2). Shipping documents shall be clearly marked with the required designation
"RQ Asbestos". Contractor shall provide a copy of this document to the City.
R. A uniform hazardous waste manifest shall be prepared by the Contractor and signed by the
Contractor each time the Contractor ships a dumpster load of Asbestos-Containing Waste
Material. The uniform hazardous waste manifest shall include the site of waste generation, the
names and addresses of the Transporter, the Contractor, and the landfill operator with
information on the type and number of asbestos-waste containers, time and date. Contractor shall
provide the consultant with signed copies of the waste manifest before each departure.
S. Contractor or his registered hazardous Waste Hauler shall transport asbestos-containing waste
material from the abatement site directly to the specified disposal site. Contractor or their Waste
Hauler shall not accept material from any other site when transporting asbestos-containing waste
material from the abatement site. The consultant reserves the right to travel with Contractor’s
Waste Hauler to the waste disposal site. No intermediate storage of waste material (i.e.
Contractors warehouse) shall be permitted.
T. Final or progress application for payments will not be processed unless all hazardous waste
manifests generated to date have been received and reviewed by the Resident Engineer.
U. All asbestos materials, wastes, shower water, polyethylene disposable equipment and supplies
shall be disposed of as contaminated waste, in accordance with the EPA regulation (40 CFR,
Section 61.150) and those requirements of the New York State Department of Environmental
Conservation and the New York Department of Sanitation.
V. Contractor shall transport all sealed drums to a landfill disposal site approved by the Department
of Environmental Conservation and the EPA. Transportation shall be performed by a New York
State registered Waste Hauler, where required. When presenting the ACW for disposal the