Asbestos Abatement
6. Installation of non-ACM replacement insulation following completion of
abatement activities shall be done by the Contractor as described in PART
6 INSTALLATION OF NON-ACM INSULATION of this Specification.
7. The Contractor shall be responsible for and shall include in its Bid any
and all fees or changes imposed by Local, State or Federal Law, Rule or
Regulation applicable to the work specified herein, including fees or
charges which may be imposed subsequent to the date of the Bid opening.
C. Contractor shall perform the following work as described below and indicated on
the drawings. The drawings are only a diagrammatic representation of the Work
Areas and do not constitute the actual quantities of material. Contractor is
responsible for the confirmation of the actual total quantities of the Work to be
performed prior to Bidding.
1. Drawing A-2: Administration Building, 5* and S* Floor Plan
a. Remove pipe and pipe fitting insulation (valves, elbows, tees, etc.)
in Work Areas 1 and 3 utilizing tent procedures as specified in
"Attachment T - Requirements for Glove-Bag Procedures Inside
Tent Enclosure" and "Attachment R - Remote Worker and Waste
Decontamination Units". A variance for utilizing these procedures
within the Work Area shall be applied for by the Contractor and
approved by the New York City Department of Environmental
Protection (NYCDEP) prior to the start of abatement activities.
Selective plaster demolition must be carried out within the tent
enclosure. Demolition debris shall be disposed of as asbestos-
contaminated materials.
b. Remove vinyl asbestos floor tiles (VAT) and associated mastic in
Work Areas 2,4 and 5 utilizing "Attachment FV - Procedures for
Use of Foam or Similar Viscous liquid in Removal of Potentially
Friable Vinyl Asbestos Tile (VAT) in New York City". A
variance for utilizing these procedures within the Work Areas shall
be applied for by the Contractor and approved by NYCDEP prior
to the start of abatement activities. When applicable, the
Contractor may utilize NYS DOL procedures upon prior approval
from the Hazmat unit of NYC DDC. There shall be no additional
cost to the City if the Contractor elects to utilize NYS DOL
procedures.
C. . Plasticize and Remove lab tops in work area 6 as Asbestos
Containing Waste Material (ACWM).
CAPITAL PROJECT NUMBER PO79201K 02081-5
100: CONTRACT DOCUMENTS REV. May 3,2000
- 5 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_0 06631254
NYC-WTC_000416766