§1-23 TITLE 15—DEPT. OF ENVIROM?.fENTAL PROTECTION
Exterior Scaffolding
Exterior trenching and drainage
Flagpoles
Kiosks
New finish material
New storefronts in existing masonry openings
Parapet Walls
Radio antenna (towers) free-standing
Relocating parking lot sheds
Replacing exterior water tanks
Replacing roof-top air conditioning unit not involving modification or
removal of ductwork
Retaining Walls
Sealing Buildings
Sealing of dumbwaiters
Sidewalk Sheds, Bridges, Fences, Elevators, Hoists, and Cafes Signs
Subdivision of an existing tax lot
Swimming pools (outdoor)
Tents
Erection of Temporary Structures (e.g., trailers, etc.) supplied with electric
and water lines only
Underpinning of Buildings
Zoning lot reapportionment
(b) ‘"Not an Asbestos Project” notification. If the cumulative total of all
surfaces affected by the work, for which plan approval is sought is not an
asbestos project, a NYC-certified asbestos investigator shall complete, sign,
and affix his or her seal to the “Not an Asbestos Project” form which shall be
submitted with an additional fee of $15.00 together with the appropriate
Buildings Department application form(s) to the NYC Buildings Department.