Page image not rendered yet. The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text
OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
tJZ)/ U f
Scope of Work:
• Remove and replace sand in playground area. Removal by use of vacuum truck.
(See note A below) 48’x26’x8”=30cy to include demolition and restoration of
pipe railings and fence required to access work area for loading & installation for
new sand approx. 30 cy $13,500-00
• Remove and replace sand in volleyball court area. Removal by use of vacuum
truck. (See note A be!ow)159x80xl2=300cy to include demolition and
restoration of pipe railings and fence required to access work area for loading &
installation for new sand approx. 250 cy $25,000,00
• Remove top 6” of soil in bocce court area. Removal by use of bobcat. (See note
A below) 55’x30'x8" = 40 cy to include demolition and restoration of pipe railings
and fence required to access work area for loading &. installation for new sand
approx. 40 cy $10,500.00
• Replace damaged railing along Pier 25. Remove and replace all wood top
handrails 500If. PowerwashTittb-eTaiTing ardngplbr?'Repair damaged curb as
needed .397,500.00
• Excavate and remove temporary asphalt roadway. Excavate and remove all
gravel under temporary roadway. Excavate and remove of soil beneath gravel to
elevation equal to bottom of the adjacent paving stone. (Between N. Moore St.
and School) (See note A below) $235,200.00
• Remove debris, patch as needed and-pewgF4vash temporary bide path. Paint lines
as required to match the existing bike path (between N. Moore St. and School)
(See note A below) $15,500.00
• Note A; All debris and sand being removed shall be coordinated with Weeks
Marine for loading up and removal via barge. This removal work to take place
during the week following the last truckload from the WTC Recovery Site.
Tentatively the last load is scheduled for 5/11/02, therefore removal to take place
between 5/12/02 and 5/17/02 (date of crane being demobilized from Pier 25).
• All repair and replacement work to occur following the demobilization of the
crane (5/17/02) from Pier 25. All repair/replacement work to be complete by June
7,2002.
• Working hours at pier 25 ai'e between 7 am and 7pm.
• Contractor to enroll in NYCDDC OCIP program with Liberty Mutual insurance.
• No sales tax to be included in the proposal.
CITY_21MC100_006525250
NYC-WTC_000386479
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000386479Source: NYC Law Department, mirrored locally