FEDERAL EMERGENCY MANAGEMENT AGENCY O.M.B. No. 3067-0151
PROJECT WORKSHEET Expires April 30, 2001
PAPERWORK BURDEN DISCLOSURE NOTICE
Public reporting burden for this form is estimated to average 30 minutes. The burden estimate includes the time for reviewing
instructions, searching existing data sources, gathering and maintaining the needed data, and completing and submitting the forms
You are not required to respond to this collection of information unless a valid OMB control number is displayed in the upper right
comer of the forms. Send comments regarding the accuracy of the burden estimate and any suggestions for reducing the burden tc
Information Collection Management, Federal Emergency Management Agency, 500 C Street, SW, Washington, DC 20472,
Paperwork Reduction Project (3067-0151). NOTE: Do not send your completed form to this address
DECLARATION NO: PROJECT NO. FIPS NO. DATE CATEGORY
FEMA- 1391 -DR- NY 808 VERSION 1 061-51000-22 03/18/03 B
DAMAGE FACILITY WORK COMPLETE AS OF:
Air/DustA/Vater Quality Testing 09/10/02 100 %
APPLICANT COUNTY
New York City, Board of Education (BoE) New York, NY
LOCATION LATITUDE LONGITUDE
PS 833-100 Trinity Place, New York, NY 10006 N/A N/A
DAMAGE DESCRIPTION AND DIMENSIONS
The collapse of the Worid Trade Centers (WTC) on September 11,2001 caused a massive cloud of concrete and dust to impact
neighboring buildings blocks away from the World Trade Center complex. Public School 833 (PS 833) commonly called the High
School of Economics and Finance is leased by the Board of Eductaion (BoE) from New York University (NYU) and is located at
100 Trinity, approximately four-tenths of a mile from the Ground Zero disaster site. The dust cloud from the collapse of the WTC
buildings directly impacted PS 833 and covered the building with several layers of dust. This dust infiltrated the building which
consists of nine floors of classroom space, one auditorium, one cafeteria, and the roof. PS 833 remained unoccupied until students
returned on February 28, 2002. This Project Worksheet (PW) addresses costs associated with air and water testing from March 1,
2002 to June 30, 2002. Costs associated with air and wafer monitoring that were incurred prior to March 1, 2002 are covered under
a seperate PW.
SCOPE OF WORK:
•“ VERSION 1
Work complete consisted of the actual expenses incurred by the New York City Board of Education (BoE) for the work performed
by ATC Associates, a contractor to BoE at Public School 833 (PS 833, also referred to as PS 489) commonly called the High
School of Economics and Finance. The total eligible work from January to September 2002 is a compilation of four payments (that
are attached to this project worksheet) and total to $634,472.45. PW 807 and 808 were based on estimates and provided the
Applicant with funds to perform the work at PS 833 totaling $415,000.40, leaving a difference of $219,472.05, which is the total
eligible additional contract cost funded under this PW. These actual invoices include the following:
Payment includes technical services costs, equipment costs and sample analyses costs to conduct air quality testing from
January to February 2002. As a result of a BoE desk audit, the payment of this voucher was reduced from 87,215.20 to
$84,085.20. The total eligible contract cost for Payment #2 was $84,085.20.
Payment #7 includes technical services costs, equipment costs and sample analyses costs to conduct air quality testing from
March to April 2002. The total eligible contract cost for Payment #7 was $279,817.25.
Payment #13 includes technical services costs, equipment costs and sample analyses costs to conduct air quality testing from
May to June 2002. The total eligible contract cost for Payment #13 was $259,440.00.
Payment #22 includes technical services costs, equipment costs and sample analyses costs to conduct air quality testing from July
to September 10, 2002. The total eligible contract cost for Payment #22 was $11,130.00.
Total eligible additional contract costs incurred by the Applicant total $219,472.05.
Does the Scope of Work change the pre-disaster condition at site? □ Yes [g No
Special Consideration issues included? [X) Yes | | No Hazard Mitigation proposal included? □ Yes No
Is there insurance coverage on facility? Yes [3] No
PROJECT COST
ITEM CODE NARRATIVE QUANTITY/UNIT UNIT PRICE COST
1 ""Version 1"" / $ $
2 9003 ATC Associates Contract 1 / LS $ 219,472.05 $ 219,472.05
/ $ $
/ $ $
ipaUll :- ______________ Total $ 219,472.05
PREPARED BY: Olivia Szabo REMARKS: Project Officer