Machine-extracted title · confidence 55%

Report of bulk sample collection at 100 Church Street for WTC-related work.

NYC-WTC_000364399–000364564
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

«» MINIMUM CONTRACTOR REQUIREMENTS accordance with applicable regulatory requirements. Filter all water used for showering and cleaning equipment through a S-micron filtration system. Dispose of water in the sanitary sewer system.

5.6 Provide temporary connection to existing building utilities or provide temporary facilities as required or as necessary to carry out the Work.

6.0 NEGATIVE PRESSURE SYSTEM (IF USED)

6.1 If needed provide ftilly operational diminished air equipment to be used as needed in each work area while cleanup procedures are in affect. The exhaust of the negative pressure system shall be directed outside of the building.

6.2 Allow exhaust units to run until completion of work area cleanup.

6.5 When a final inspection and the results of final air tests indicate that the area has been decontaminated, HEPA filtration system shall be removed from the work area in conjunction with the isolation barriers.

7.0 SECTION NOT USED

8.0 WORKER DECONTAMINATION PROCEDURES

8.1 Require all workers to adhere to the following personal decontamination procedures whenever they leave the work area:

a) When exiting area, remove outer layer of disposable coveralls, disposable head covers, and disposable footwear covers or boots in the first airlock at the exit of the tent enclosure.

b) Still wearing respirators and remaining layer of disposable covering, proceed to remote shower unit and follow procedures as outlined for worker decontamination.

9.0 ASBESTOS REMOVAL

9.1 All horizontal surfaces within each respective work shall first be cleaned with a HEPA vacuum followed by wet wiping with amended water. When dry die area shall be cleaned again using a HEPA filtered vacuum.

9.2 All items not to be discarded shall be cleaned and decontaminated and left in-place. Coordinate with Tenant Representative prior to discarding any items that cannot be decontaminated.

9.3 In areas where clothing items are present, decontaminate the item by first using a HEPA vacuum, followed by wet wiping and followed again by HEPA vacuum after the item has dried.

9.4 All non-porous personal items on work desks shall be HEPA vacuumed, wet wiped and again HEPA vacuum. Place all items desk. All porous personal items (suit case, purse, shoes, etc.) shall be HEPA vacuumed, wet wiped and again HEPA vacuumed. Place in REMOVAL OF ACM DUST PAGE 6 ZARReedty Selected Floors/Areas 100 Church Street

CITY_DEP_WORBY_CANNATA_SUBP_000001846

NYC-WTC_000364406

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000364406Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →