Status of DEP nonpoint source projects, 2001

Machine-extracted title · confidence 49%

Status report on DEP nonpoint source pollution projects and activities, Jul–Sep 2001.

NYC-WTC_000290962–000291014
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

♦ The exposed portion of the upstream side of the dam embankment at basin 2 is comprised of medium sized rip rap. To appease neighbors, DEP placed an erosion control mat over the approximately 7000 square feet of rip rap to shield it from view. To further satisfy the same neighbors, DEP topdressed the embankment after obtaining a NYSDEC permit. The preconstruction meeting for topdressing v/as held in August and the work was completed in September 2001. Staff continued to discuss existing and new enhancements with the neighboring property owner after topdressing was in place.

♦ DEP finished planting three ornamental trees and 16 evergreen trees to shield the view of the dam embankment at basin 2A from a neighbor. DEP regularly inspected and watered the trees. DEP continued to discuss enhancements after the plantings were installed.

Regulator)) Approvals

New York State Department of Environmental Conservation

♦ Upon receipt of approved as-built drawings, The Department will request NYSDOT complete its final inspection and approve construction of facilities 66, 67, and 68.

Faeilitv Construetion

The Department divided construction of the stormwater management facilities into three phases. Phase 1 includes six facilities in the Malcolm and Young Brook subbasins, excluding the extended detention basin on Pepsico property. Phase I facilities discharge to tributaries located within approximately 500 feet of the Catskill Upper Effluent Chamber. Phase II of the construction includes the facility on the Pepsico site located at the headwaters of Malcolm Brook. The final phase. Phase III, includes the remaining facilities throughout the Kensico watershed.

Phases I and // - Facilities in the Malcolm Brook and Young Brook Subbasins

Construction was completed in December 2000.

Phase III - 37 Facilities in the Subbasins ofN2 through Ell

♦ The three-year construction contract began on October 12, 1999. ♦ At the end of the reporting period, 40 facilities were operational. Facilities 58, 59, 74 and 75 were redesigned. The revised designs were under review by regulatory agencies and the Mayor’s Office of Design and Construction at the close of the reporting period. 0 All of the landscaping was completed and post-construction photographs were taken. ❖ Draft as-built drawings were received and reviewed. DEP issued substantial comments.

18

NYC-WTC_000290981

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000290981Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000137900

Archival folder label for Department of Environmental Protection biweekly reports related to World Trade Center activities from 2000 to 2001.

Similar indexed content

Compare copies and versions →