NYC 9/11 Public Portal Document
Asbestos Inspection Report
Premise No. Inspection Date:
130 Liberty Street 10/28/08
Floor Zip Borough Block Lot Squad # Badge #
Various______ ____ 10006 1 54 1 1 AO61
Inspector Building Type Basis of Inspection Photos Taken
H. Guirguis A TRU0086MN08 NO
Contractor's Name Sample Number
JArt^nyiranmen^
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner’s Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1430 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 10006 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj. Mgr./TRC Environmental 08:00am - 09:00am
On arrival I met Nugent Gerald, Supervisor for LVI Environmental at the LVI field office, who informed me that a total of 1
Handler Supervisor and 30 Asbestos Handlers were in the 6”’ floor today for the first shift.
The daily work schedule informed me of the following:
1. 11"' floor: 32 men- scraping area 11-13, box debris.
2. 8"' floor: 34 men- demo, boxing debris, putting platform across shafts
3. 7"’ floors: 3 men- demo, boxing debris
4. 6'*’ floors: 30 men- demo, boxing debris
4, Various floors : 12 men loading out boxes to ATC trailer
After signing the log book donned personal protection and accessed the work areas.
1. 6'" floor: workers were found in the process of Demo, boxing debris; there was still a lot of wet debris on the floor,
demolition was not completed, workers were cutting metals using power tools, HEPA vacuum attached with the
power tools, fine spraying amended water in the work area, preparing Gaylord boxes. Inspection was done on the
Micro trap Machines and the Micro trap tents and on all the work area
I used the stairs to go to the 7'" floor
2 7’”, 9*" and 10"’ floor: There were no activity or personnel observed on the floor
Gaylord boxes and numerous poly wrapped beams were on the floor ready to be taken out
3. s’" floor: workers were found in the process of demo, boxing debris, putting platform across shafts, fine spraying
amended water on the Gaylord boxes, poly wrapped beams and the work area, preparing Gaylord boxes and poly
wrapped beams,
Inspection was done on the Micro trap Machines and the Micro trap tents. 20 Micro trap Machines were powered
on and 5 were on stand by,
Gaylord boxes and numerous poly wrapped beams were on the floor ready to be taken out
4, 11"’ floor: workers were found in the process of cleaning the floor, the beams and wet wiping the walls, HEPA
vacuuming the floor, preparing Gaylord boxes
Inspection was done on the Micro trap Machines and the Micro trap tents. 20 Micro trap Machines were powered
on and 5 were on stand by,
I used the stairs to get to the S'" floor.
I exited the work area after decontaminating and signing the log book.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s Initial
Borough l=ManhaCtan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code 1 = Violation Issued 2=No Violation Issued 3=No access 4=Project not started (no NOV)
5-Publit Owned Propeily
CITY_DEP_WORBY_CANNATA_SUBP_000130502
NYC-WTC_000181907