Description of work Reason for change & Amount of Amount
who requested change proposal approved
1 Offset wall/relocate ductwork Site conditions $10,817.00 $7,000.00
2 Baltimore Air Coil circuit cooling 5(516 $6.00
3R Miscellaneous electrical changes Change of spec by architect/agency $3,704.00 $3,704.00'
4R Bulletin #1
1 Cost relating to incorporating comments of port authority Deletion of work as per PA comments -$2,950.00 -$18,308.00
2 Cost for deletion of A/V works and equipments Deletion of work by agency
3. Hurricane wall
a) Construction of hurricane wall Upgrading of hurricane wall by agency $331,310.00 $281712.00
b) Motorize hurricane wall dampers Upgrading of hurricane wall by agency $135,906.
5
6 Additional cost approved for changing door #01A to bullet resistant Upgrading of door by agency $406.00 $406.00
7R void $0^ $0.00
8 Additional cost approved for changing door #01B and surrounding area
to bullet resistant Upgrading of door/wall by agency $11,688.00 $11,688.00
9 Additional cost approved for changing door finish from painted
to Mahore finish Upgrading of finish by agency $11,707.00 $11,707.00
10 Additional cost approved for providing class I package
receiver as per sketch prepared by SHCA Upgrading of security by agency $2,666. [ililMTOTiial
Additional amount approved for revision of drawings with
respect to the above refeired door/package receiver Additional item requested by agency $1,975.00 $1,975.00
11 Change door #5 from HM to ACME partition door Change of spec, by agency $2,898.00 1^,898.00
12 Provide Volt meter & ammeter Additional item requested by agency $7,766.00' $7,766,00
13 Additional framing/sheetrock at door frames & fascia Upgrading of work by agency $985.00 $985.00
14 Credit for deletion of witnessing of field test for emergency
generator by Cosentini Associates Deletion of work -$5,216.00 -$5,216.00
15 Additional 4’’ & 2" sleeves, 4” stub-up and associated cutting
and patching on 23rd floor Additional work requested by DolTT $21,234.00 $21,234.00’
Additional architectural fee for scope revisions Additional item requested by agency $2,375.00 $2,375.00
16R Changes in Panel boards Additional item requested by agency $21,519.00 $18,500.00
17R F&l combination floor boxes under raised floor area as per architect Change of spec, by architect/agency $5,042.00, $5,042.00
Additional fee for SHCA for revision to drawing for Micwwave dish location Additional work requested by agency $2,525.00 $2,525.00
18 Replace projectors with upgraded projectors 16761 $0.00
19 42" X 30" decoustic panels Change of spec, by architect/agency $4,636.00 $4,636.00
20 Provide power for fan power boxes from various panels lieu of one panel Design changes
21 Additional structural steel at switch gear area and water tank Design changes due to site conditions
22R F&l (2) 6 strand and (1) 24 strand multi-mode fiber Additional item requested by agency $6726.00 $6,728.00
23 Additional work on 7th floor as per sketch from Cantor Additional work due to site conditions $7,534.00 $5,800.00
24R Control wiring to 60 monitors & 4 LCD video projectors in EOC & Watch Command Additional item requested by agency $3,001.00 $3,001.00
25 Structural support for Microwave dishes Additional item requested by agency $36^99.00 $34,500.00
26R Additional work as per SHCA sketches FSK-37, 38, 12&40 Additional item requested by agency $12,599.00' $10,800.00
27 Credit for painting LAN room floor in lieu of VCT flooring -481 $0.00
28 Independent feed to ELP-23N & ELP-23N-1 Additional item requested by agency $1,478.00 $1,478.00
29 Additional 2 duplex outlets and 1 switch in PDU/Training room #23-42 Additional item requested by agency $464.00
30 Additional cost as per sketches FSK-47 & 41 Additional item requested by agency $1,391.00 $1,391.00
31 F&l security wire in conduit as per Vikonics spec #11020-C Additional item requested by agency $54754.00 $52,008.00
32 New coat closet as per FSK44 at room #23-09 6694 $0.00
33 Additional cost for sleeves and grounding Additional item requested by agency $5,908.00 $5,008.00
34 F&l new metal cap flashing w/drip return as shown on the Kemper system drawing Extra work requested by Kemper due to site conditions $1791.00 $1,391.00
35 Termination of fiber optic cables & furnishing of patch panels Additional item requested by agency $5796.00 $5796.00
36 Water proof the generator room on the 7th floor with Dex-o-Tex floor 17126 $0.00