37 F&l stainless steel cladding to 20 existing window mullions ^10166 $0.00
38 Additional drains as per SKP 3 and SKP 4 in HC toilet rooms 23-3 & 23-32 Additional item requested by agency $8,346.00 $7,000.00
39R Mobile PBF 15’Wx 17 3/4" D LN Novatink furniture not included in base bid Items excluded in the bid but required $26,391.00 $26,391.00
40 Chop concrete and weld new rebar to existing rebar in trench w/3" overlap Additional work due to site conditions $26,42>.OO
41 Antenna support per revised sketch from Cantor adding 4 steel clips welded to web Additional work due to site conditions $16,807.00 $14,500.00
42 F&l 4 type G wall washers in room #23-40 as per FSK-51 2202 $0.00
43 RG-6U plenum cable for Time & Warner TV as per John Hughes letter Additional item requested by agency $11,759.00 $11,000.00
44R F&l oil piping as per revised routing sketch FSK50 & SK58 dated 3/19/99 Additional work due to site conditions $85,893.00 $85,000.00
45 F&l 1 custom press panel & installation & termination of cables in to it Additional item requested by agency $1,430.00 $1,430.00
46 Additional electrical work in room 23-50 and 23-18 for power supply/sequrity equip 2168 $0.00
47 Furnish 3 stainless steel flexes for the generators Additional work due to site conditions $3,941.00 $3,941.00
48 Additional work as per Swanke memo dated12/29/&8 Additional item requested by agency $4,679.00 $4,679.00
49 Change ceiling tile & sprinklers in press room Changes requested by agency $6779.00 $6,779.00
50 Correct incompatability between Ace video equip & Lutron dimming system Additional work due to site conditions $1,O67.0g| $1,067.00
51 Various changes in storage room shelving units Additional item requested by agency $751.00 $751.00
52 Various electrical changes as per RB Samuel’s work orders Changes requested by agency $38,987.00 $36,060.00
53 Various electrical changes as per RB Samuel’s woik orders Changes requested by agency $2,898.00 $2,898.00
54 Man hour cost for moving computer equipments on 23rd floor Additional item requested by agency $2,671.00 $2,671.00
55 Removal /reinstallation of electrical work due to new routing of fuel line Additional work due to site conditions $34,954.00 $29,000.00
56 1 duplex outlet on 1 st floor with cable in 1" conduit 1^9242 $0.OO
57 Additional equipment & labour for security work as per SHCA memo dated 12/17/98 Additional item requested by agency $68,613.
58 Labour for moving computer equipments Additional item requested by agency $5,506.
59 1 duplex outlet on 1 st floor w/wiring through existing 4" conduit Additional item requested by agency $10,948.
60 Close gap at steel in hurricane wall w/16 gauge steel plate as per FSK-54 Additional work due to site conditions $8,114.00 $8,114.00
61 Mag tock over ride button for doors at toilet rooms, water storage room,bunker rooms
and door leading to bunker room area Additional work due to site conditions $2,785.00 $2,400.00
62 Roof repair as per details at new curb from Kemper system Extra work requested by Kemper due to site conditions $9,679.00 $9,679.00
63 Additional electrical work as per RB Samuels work orders Changes requested by agency $1,912.00 $1,912.00
64 Additional electrical work as per RB Samuels work orders Changes requested by agency $7 J 14.00 $6,500.00
65 X-Ray machine and badging system Additional item requested by agency $26,336.00 $22721.00
66 Press room floor and podium Changes requested by agency $15,460.00 $14,866.00
67 Various electrical changes as per RB Samuel’s woik orders Changes requested by agency $2,894.00 $2,894.00
68 F&l astragal on door #5 ACME pair of doors $0.00
69 F&l closer, roof chain and provide additional keys Additional item requested by agency $786.00 $672.00
70 Three (3) 28" dia. And Two (2) 21" dia. Cast magnum plaques Additional item requested by agency $6,114.00 $6,114.00
71 3 phase 30 amp wiring for circulating pumps Additional item requested by agency $4,579.00 $4,579.00
72 F&l Two (2) Alto Shaam cooking and holding oven model 1000-THI/HD/D Additional item requested by agency $11,539.00
73 Furnish two (2) Luxor TVP44 -44" TV cart for PIU room monitors Additional item requested by agency $1,580.00
74 F&l blackout shade bands for press room & Mayor's (xjnference room $4,631.00
75 F&l (2) two UPS units Additional item requested by agency $4,874.00 $4,874.00
76 Relocate existing cold water make-up line as requested by Building Engineers Site conditions $701.00
A&E fee for additional Audio-visual scope of work $18,560.00
77 Dam closure, flashing and Aluminum drip pan at radio room on the roof Site conditions $24,274.00
78 Various work by RB Samuels/Precision Interiors/Miller Druck Changes requested by agency $7716.00
79 F&l one hundred additional reinforcing plates for the blast proof & access doors Additional item requested by agency $6,955.00
80 Removal of additional granite flooring regarding fuel oil pipe work Site conditions $1,631.00
81 Fasten radio room walls to the structural steel with special clips Additional item requested by agency $6,228.00
82 Replace door & frame of radio room with blast resistant door Additional item requested by agency $8,313.00
Total $1,013,670.00 $775,877.00