Breakdown of approved change orders, OEM project, Feb 17, 1999

Machine-extracted title · confidence 90%

Financial breakdown of approved change orders for the Mayor's Office of Emergency Management, including costs for ductwork and electrical changes.

NYC-WTC_000173949–000173950

Folder label: “Breakdown of Approved Change Orders

Page image
Scanned page image, NYC-WTC_000173949
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Mayor's Office of Emergency Management 7 World Trade Center

2/17/99 Breakdown of approved Change Orders

Description of work Amount of Approval Amount proposal date approved Remarks

1 Moving wall/relocate ductwork $10,817.00 8/11/98 $7,000.00 Apptroved $7,000.00 2 Baltimore Air Coil circuit cooling 9818 $0.00 __ v£id_ $0.00 3R Miscellaneous electrical changes $3,704.00 9/14/98 $3,704.00 Appiroved $3,704.00 4R Bulletin #1 1. Cost relating to incorporating comments of port authority -$2,950.00 9/14/98 -$18,308.00 Apptroved -$18,308.00 2. Cost for deletion of A/V works and equipments -$270,024.00 9/14/98 -$289,803.00 Appiroved -$289,803,00 3. Hurricane wall a) Construction of humcane wail $331,310.00 9/14/98 $281,112.00 Approved $281,112.00 b) Motorize hurricane wall dampers $135,906.00 9/14/98 $126,000.00 Approved $126,000.00 5 void void 6 Additional cost approved for changing door #01A to bullet resistant $406.00 9/21/98 $406 00 Approved $406.00 7R void $0.00 $0 00 void $0.00 8 Additional cost approved for changing door #01B and surrounding area to bullet resistant $11,688.00 9/21/98 $11,688.00 Approved $11,688.00 9 Additional cost approved for changing door finish from painted to Mahore finish $11,707.00 9/21/98 $11,707.00 Approved $11,707.00 10 Additional cost approved for providing class I package receiver as per sketch prepared by SHCA $2,666.00 9/21/98 $2,666.00 Approved $2,666.00 Additional amount approved for revision of drawings with respect to the above referred door/package receiver $1,975.00 9/21/98 $1,975.00 Approved $1,975.00 11 Change door #5 from HM to ACME partition door $2,898.00 10/22/98 $2,898.00 Appiroved $2,898 00 12 Provide Volt meter & ammeter $7,766.00 10/30/98 $7,766.00 Appiroved $7,766.00 13 Additional framing/sheetrock at door frames & fascia $985.00 10/30/98 $985.00 Appiroved $985.00 14 Credit for deletion of witnessing of field test for emergency generator by Cosentini Associates -$5,216.00 10/22/98 -$5,216 00 Appiroved -$5,216.00 15 Additional 4" & 2" sleeves, 4" stub-up and associate d cutting and patching on 23rd floor $21,234.00 10/22/98 $21,234.00 Approved $21,234 00 Additional architectural fee for scope revisions $2,375.00 12/1/98 $2,375.00 Approved $2,375.00 16R Changes in Panel boards $21,519.00 12/1/98 $18,500.00 Approved $18,500.00 17R F&l combination floor boxes under raised floor area as per architect $5,042.00 10/22/98 $5,042.00 Approved $5,042.00 Additional fee for SHCA for revision to drawing for Microwave dish location $2,525.00 10/22/98 $2,525.00 Approved $2,525.00 18 Replace projectors with upgraded projectors 16761 $0.00 VOID $0.00 19 42" X 30" decoustic panels $4,636.00 10/30/98 $4,636.00 Approved $4,636.00 20 Provide power for fan power boxes from various panels lieu of one panel $12,866.00 10/30/98 $11,000.00 Approved $11,000.00 21 Additional structural steel at switch gear area and water tank $20,342.00 10/30/98 $18,500.00 Approved $18,500.00 22R F&l (2) 6 strand and (1) 24 strand multi-mode fiber $6,728.00 12/1/98 $6,728.00 Approved $6,728.00 23 Additional work on 7th floor as per sketch from Can :o< $7,534.00 1/25/99 $5,800.00 App>roved $5,800.00 24R Control wiring to 60 monitors & 4 LCD video projectors in EOC & Watch Command $3,001.00 12/1/98 $3,001.00 Approved $3,001 00 25 Structural support for Microwave dishes $36,199.00 12/1/98 $34,500.00 Approved $34,500.00 26R Additional work as per SHCA sketches FSK-37, 38,12 & 40 $12,599.00 1/25/99 $10,800.00 Approved $10,800.00 27 Credit for painting LAN room floor in lieu of VCT flooring -481 $0.00 __ VOID $0.00 28 Independent feed to ELP-23N & ELP-23N-1 $1,478.00 12/1/98 $1,478.00 Approved $1,478.00 29 Additional 2 duplex outlets and 1 switch in PDU/Traming room #23-42__________ ________ $464.00 12/1/98 $464.00 Approved $464.00 30 Additional cost as per sketches FSK-47 & 41 $1,391.00 12/1/98 $1,391.00 Approved $1,391.00 31 F&l security wire in conduit as per Vikonics spec #11020-c $54,354.00 12/1/98 $52,008.00 Approved $52,008.00 32 New coat closet as per FSK44 at room #23-09 6694 $0.00 VOID $0.00 33 Additional cost for sleeves and grounding________ $5,008.00 12/1/98 $5,008.00 Approved $5,008 00 34 F&l new metal cap flashing w/drip return as shown or the Kemper system drawing $1,391.00 1/25/99 $1,391.00 Approved $1,391.00 35 Termination of fiber optic cables & furnishing of patcti panels 5796 $0.00 VOID $0.00 36 Water proof the generator room on the 7th floor with Dex-o-Tex floor 17126 $0.00 VOID $0.00

NYC-WTC_000173949

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173949Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Breakdown of approved work costs, MOEM, July 1999 · Box 7DCAS

NYC-WTC_000172947

Document dated July 12, 1999 listing approved change orders and costs for construction work at the Mayor's Office of Emergency Management in 7 World Trade Center.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.979

machine-extracted · confidence unavailable · Check page ↗
MOEM approved work breakdown, June 1999 · Box 7DCAS

NYC-WTC_000172970

Document listing approved costs for ductwork, electrical changes, and hurricane wall construction at the Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.971

machine-extracted · confidence unavailable · Check page ↗
Breakdown of approved construction costs, April 2002 · Box 7DCAS

NYC-WTC_000171286

Document dated April 12, 2002 listing approved costs for various construction items including wall relocation and hurricane wall work at the Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.963

machine-extracted · confidence unavailable · Check page ↗
OEM breakdown of approved change orders, Nov 1998 · Box 7DCAS

NYC-WTC_000173552

Itemized list of approved change orders for the Mayor's Office of Emergency Management at 7 World Trade Center, including costs and approval dates.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.959

machine-extracted · confidence unavailable · Check page ↗
OEM budget breakdown for 7 WTC project, November 1998 · Box 7DCAS

NYC-WTC_000173554

Budget accounting document detailing construction costs, revised budgets, and change order approvals for the Mayor's Office of Emergency Management at 7 World Trade Center.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.954

machine-extracted · confidence unavailable · Check page ↗
OEM breakdown of approved change orders, Nov 1998 · Box 7DCAS

NYC-WTC_000173550

Itemized list of approved change orders for the Mayor's Office of Emergency Management at 7 World Trade Center, including costs and approval dates.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.952

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →