Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
Same agency, volume and box · similarity 0.932
machine-extracted · confidence unavailable · Check page ↗Revised electrical work proposal from ADCO Electrical Corporation for the Mayor's Office of Emergency Management on the 26th floor at 7 World Trade Center in May 1998.
NYC-WTC_000172686–000172689Folder label: “Mayor's OEM®7 World Trade Center®26th Floor (Revised)”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
Sheetl Transformers 75 KVA 2 4600 9200 9300 Transformers 45 KVA 1^ 3600 3660 Transformers 30KVA 1 2500 2555 Transformers 37.5KVA T 2800 2891 Transformers 15 KVA 1 2200 22^
Automatic Transfer Switch #1, 2000A Prepurchased 3372 ATS#27MOA r ^00 9300 1591 ATS#3, 400A 7 2 5775! 5775 1281 ATS #4, AfS'#5',200A 3990, 1049 ATS # 6, 200A 7 4000 1049 ATS#7r200A 4000 1049 ATS^,2£0A 4000 1050 ATS#9, 100A 2517 2500 1049
meter 2MililA 1 3600 3600 3609 meter 800A______ 2 3000 6000 5340 meter 200A 2 2000 4i •52 4000 Service Switch Fuse 2000A T 10000 1 “ 10076 tapping to existing 5000 EDPH-23, 277/480V, 3Ph, 4W- 1 1 ZZ 22540 panel, 277/480V, 3 ph 31001t 18600 Inc in 136000 panel, 120/208 V, 42 CB 7 22 3000 r 66000 136000 bus ducts 800/600 A P 11700 11700 panerboardf2y7/480Vr^ole7Twire200A 19 2400 45600 200 A Disconnect Swtch Telephone riser + pull wires 700LF ;45/LF 31500 224000 Tel outlets + Stubups 240 100 24000 137700 Tel /data cabling ! 198000 Furniture Devices 159000 Plugmold & Isoduct 16000 Eng & Drafting TooT-2.5% Cable/tray L-1RMD 90000 53000 Audio/ Visual 177000 Security System 176000 - -i- - CCW 7 7 _J 22000 Fire Alarm 100000 114000 Preaction 10000 18000 Supervision 9? 185000 total 2224545 3815377
Page 2
NYC-WTC_000172689
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
Same agency, volume and box · similarity 0.932
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173881
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
Same agency, volume and box · similarity 0.929
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168639
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
Same agency, volume and box · similarity 0.929
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.
Same agency, volume and box · similarity 0.926
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172684
Revised electrical work proposal from Forest Electric Co. for the Mayor's Office of Emergency Management at 7 World Trade Center covering multiple floors.
1 shared non-person entities · Same agency, volume and box · similarity 0.917
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171897
Ambassador Construction submits Change Order #016R for electrical work at the Mayor's Office of Emergency Management on November 13, 1998.
Same agency, volume and box · similarity 0.917
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168645
Revised Change Order #16 submitted for electrical work at 7 World Trade Center dated October 19, 1998.
Same agency, volume and box · similarity 0.916
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171903
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
Same agency, volume and box · similarity 0.915
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168642
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
Same agency, volume and box · similarity 0.915
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173254
A letter detailing the installation of graphic annunciator panels and wiring for generators at the Mayor's Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.913
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000105155
Invoice enclosing bulk sample results, air monitoring data, and cleanup summaries for 17 Battery Place.
1 shared non-person entities · similarity 0.913
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000135975
Document containing illegible text or corrupted data within the Department of Environmental Protection's Athena D Terms records.
1 shared non-person entities · similarity 0.912
machine-extracted · confidence unavailable · Check page ↗Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
Similar indexed content
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
Similar indexed content
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
Similar indexed content
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.