AMBASSADOR CONSTRUCTION CO., INC. _______________
March 31. 1999
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE; Mayor's Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #077
Amb. iQb # S57-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #077 to perform the following work at
the above referenced premises for the sum of TWENTY FOUR THOUSAND TWO
HUNDRED SEVENTY FOUR DOLLARS ($24,274.00);
SCOPE OF WORK
- Furnish and install two (2) aluminum dam closures
where new panel walls abut existing wall system.
- Remove existing louver and install continuous flashing
and re-install louvers.
- Furnish and install ail aluminum drip pan @ back
concrete curb. Panel & Flashing Work $20,942.00
General Conditions 1,675.00
Overhead & Fee 1,357.00
Insurance 300.00
Total $24,274.00
NOIE:
Additional flashing details as per Swanke Hayden Connell’s office sketches 52 and 52A
dated 1/29/99 attached.
Please notify us if we are to proceed with this work.
^j^SSADOR CONSTRUCTION CO., INC.
____________
Martin Schneider
Vice President
MS:am
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted:______________ Dated;
c \0PFICE\WPWIN\WP00CS\0eM\C0-S\OEMC077 WPD
317 MADISON AVENUE • NEW YORK, NY 10017 - 212 922 1020 • FAX 212 949 9762
NYC-WTC_000172146
OCR can misread numbers and units. Confirm readings against the page image before using them.