DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES
H DIVISION OF REAL ESTATE SERVICES
MUNICIPAL BUILDING, - Room 2002 S
NEW YORK, N.Y. 10007
(212) 669-8086 FAX (212) 669-3 640
V/ILLIAM J, DIAMOND LORI FIERSTEIN
Commissioner Deputy Commissioner
February 28, 2000
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re: Change Order # 111 & 112
Mayor’s Office of Emergency Management
7 World Trade Center
New York, NY
Dear Ms Giliberti:
We write with reference to CO submitted by Ambassador Construction Company on
1/28/00 & 2/14/00. The proposals are in the amounts of $17,466.00 for electric space heaters & insulating
the generator room walls on 7* floor and $2,266.00 for providing check valve in place of anti-siphon valve
on the oil pump suction pipe respectively.
The change orders have been reviewed and the costs have been found fair and reasonable.
Therefore, in view of the foregoing, an amount of $19,732.00 is hereby approved, subject to audit, for the
above change orders.
The following is a breakdown of the project’s budget;
Construction Cost Budget (revised) $14,287,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/21/98 $ 102,705.00
Amount approved by CO on 10/22/99 $ 28,442.00
NYC-WTC_000171502