9.2 SPI noted that their security consultant/vendor has recently upgraded the base building
security system and the OEM security system should be coordinated with base
building. SHCA noted that security measures or procedures that require access to base
building areas need to be coordinated (i e.- Mayor’s vehicle entering to the Loading
Dock and providing a secure access from the Loading Dock to the service elevators).
10.0 Architectural Design Presentations
10.1 SHCA was to have presented preliminary lighting design, the reflected ceiling layout SHCA/OEM/DCAS
and materials/finishes to OEM. Due to Q. Hauer's unavailability, this presentation
has been rescheduled to 01 '20/98 at SHCA’s office.
cc: C. Meinhaidt-SHCA
D. Recker-ETI
rniRnko Umirian Pnnnall 1 til iTnrnnka Unuilan PnnnaH ft nnrtiiarn T T B
NYC-WTC_000170878
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000170878Source: NYC Law Department, mirrored locally
Facsimile message dated February 24, 1998 distributing copies of a document regarding the Mayor's Office of Emergency Management at 7 World Trade Center.
5 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.962
Cover sheet for a fax transmission regarding architectural and engineering design services for the Mayor's Office of Emergency Management at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.936
Department of Citywide Administrative Services approves the selected architectural and engineering consultant team for the Mayor's Office of Emergency Management project.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.935
Letter from a consultant submitting a proposal for architectural and engineering design services for the Mayor's Office of Emergency Management at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.932
Architectural firm proposal for design services for Mayor's Office of Emergency Management center at 7 World Trade Center, including scope of work and consultant proposals, dated…
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.928
Memo documenting DCAS/OEM approval of architectural sketches and supporting data for 7 World Trade Center emergency management facility following design review meeting.
DCAS approval of architectural and mechanical engineering services proposal for Office of Emergency Management emergency systems and equipment at 7 World Trade Center.
DCAS approval of SHCA proposal to perform architectural, structural, and mechanical engineering services for 7 World Trade Center Mayor's Office of Emergency Management.
Department of Citywide Administrative Services approves architectural and engineering services proposal for the Mayor's Office of Emergency Management at 7 World Trade Center.
Daily activity report detailing updated identification requirements for DEP employees and contractors entering the Red Zone at the World Trade Center site.